2342 S COCHRAN AVE 90016
Certificate Information: 2342 S COCHRAN AVE 90016
- Application / Permit
- 21016-10000-51784
- Plan Check / Job No.
- B21LA21043
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR AND EXTERIOR REMODEL TO EXISITNG SFD PER WFPP
- Permit Issued
- Issued on 11/22/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/1/2023
Permit Application Status History
| Submitted | 11/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | STARR CHEN |
| Corrections Issued | 12/5/2021 | STARR CHEN |
| Quality Review Completed | 12/14/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/16/2021 | APPLICANT |
| Plan Check Approved | 9/13/2022 | STARR CHEN |
| Issued | 11/22/2022 | APPLICANT |
| Permit Finaled | 11/28/2023 | JOSE AVILA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/30/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | JOSE AVILA |
| Gas Test | 12/14/2022 | Partial Approval | JOSE AVILA |
| MERV13>=Rough | 12/14/2022 | Partial Inspection | JOSE AVILA |
| PLUMBING-Rough | 12/14/2022 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 12/19/2022 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 12/19/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 12/19/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 12/19/2022 | Approved | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 12/19/2022 | Approved | JOSE AVILA |
| Insulation | 12/22/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 12/22/2022 | Approved | MICHAEL LEWIS |
| Shower Pan | 12/22/2022 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 12/30/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 11/14/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 11/14/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 11/14/2023 | Corrections Issued | JOSE AVILA |
| MERV13>=Final | 11/14/2023 | Approved | JOSE AVILA |
| MERV13>=Rough | 11/14/2023 | Approved | JOSE AVILA |
| PLUMBING-Final | 11/14/2023 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 11/14/2023 | Approved | JOSE AVILA |
| Final | 11/28/2023 | Permit Finaled | JOSE AVILA |