10801 W TUXFORD ST 91352

Certificate Information: 10801 W TUXFORD ST 91352

Application / Permit
21016-10000-51764
Plan Check / Job No.
B21LA21029
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING ONE STORY DETACHED GARAGE WTIH 7.75'x8.75 ADDITION INTO A DETACHED ADU (488 SQ.FT) per LAMC A.33 (c) AND (d)
Permit Issued
Issued on 5/5/2022
Issuing Office
Current Status
CofO Issued on 2/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 AUNG SOE
Corrections Issued 11/22/2021 AUNG SOE
Applicant returned to address corrections 1/11/2022 LUKE GONZALES
Plan Check Approved 1/27/2022 LUKE GONZALES
Building Plans Picked Up 1/28/2022 APPLICANT
Issued 5/5/2022 APPLICANT
CofO in Progress 1/17/2023 DAVID ANDERSON
CofO Issued 2/4/2023 MICHAEL SMITH
Permit Finaled 2/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/9/2021 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 12/9/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 12/9/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 12/20/2021 JOSE DUARTE-DIAZ
Specific Plan Cleared 12/20/2021 PEGGY MALONE-BROWN
Grading Pre-Inspection Cleared 12/21/2021 SERGIO VALENZUELA

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/28/2022 Approved DAVID ANDERSON
PLUMBING-Rough 7/28/2022 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 8/11/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 8/29/2022 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 8/29/2022 Corrections Issued DAVID ANDERSON
Green Building Rough 8/29/2022 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 8/29/2022 Corrections Issued DAVID ANDERSON
Special/Order Compliance 8/29/2022 Corrections Issued DAVID ANDERSON
Wood Frame 8/29/2022 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 9/12/2022 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 9/12/2022 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 9/15/2022 Approved DAVID ANDERSON
Rough-Elec/Plmb/HVAC 9/15/2022 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 9/20/2022 Approved DAVID ANDERSON
ELECTRICAL-Rough 9/20/2022 Approved DAVID ANDERSON
Final 9/20/2022 Corrections Issued DAVID ANDERSON
Green Building Rough 9/20/2022 Approved DAVID ANDERSON
HVAC-Rough 9/20/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 9/20/2022 Approved DAVID ANDERSON
Insulation 9/30/2022 Approved DAVID ANDERSON
Drywall Nailing 10/6/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 10/19/2022 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 10/28/2022 Approved DAVID ANDERSON
Shower Pan 10/28/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/1/2022 Approved DAVID ANDERSON
Final 1/10/2023 Corrections Issued DAVID ANDERSON
Green Building Final 1/10/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 1/10/2023 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 1/10/2023 Approved DAVID ANDERSON
Final 1/13/2023 OK to Issue CofO DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Approved DAVID ANDERSON
Service/Power Release 1/17/2023 Approved DAVID ANDERSON