2114 3/4 S RIDGELEY DR 90016

Certificate Information: 2114 3/4 S RIDGELEY DR 90016

Application / Permit
21016-10000-51575
Plan Check / Job No.
B21LA20952
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePlan Check* CONVERT DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) ALL WORK PER WFPP
Permit Issued
Issued on 5/18/2022
Issuing Office
Current Status
CofO Issued on 1/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2021 APPLICANT
Assigned to Plan Check Engineer 11/16/2021 MONICA RAMIREZ
Corrections Issued 11/17/2021 MONICA RAMIREZ
Applicant returned to address corrections 4/7/2022 MONICA RAMIREZ
Plan Check Approved 4/20/2022 MONICA RAMIREZ
Issued 5/18/2022 APPLICANT
CofO in Progress 1/24/2023 JOSE AVILA
Permit Finaled 1/30/2023 DEROLD HAUFF
CofO Issued 1/30/2023 DEROLD HAUFF
Permit Finaled 1/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/2/2021 WALLIE JONG
Sewer availability Cleared 12/2/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/20/2021 WALLIE JONG
Construction near power lines Cleared 3/12/2022 RIDWAN HARDY

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/24/2022 Approved JOSE AVILA
Footing/Foundation/Slab 9/1/2022 Approved JOSE AVILA
Deputy Drilled-In Anchors 9/14/2022 Conditional Approval JOSE AVILA
Deputy Drilled-In Anchors 9/23/2022 Conditional Approval JOSE AVILA
HVAC-Rough 10/3/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 10/3/2022 Partial Approval JOSE AVILA
ELECTRICAL-Rough 10/6/2022 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Approved JOSE AVILA
PLUMBING-Rough 10/6/2022 Approved JOSE AVILA
Insulation 10/12/2022 Approved JOSE AVILA
Interior/Exterior Lathing 10/12/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 10/18/2022 Approved JOSE AVILA
Drywall Nailing 10/18/2022 Partial Approval JOSE AVILA
Green Building Rough 10/18/2022 Approved JOSE AVILA
Interior/Exterior Lathing 10/18/2022 Approved JOSE AVILA
Drywall Nailing 11/1/2022 Partial Approval JOSE AVILA
Underground Mechanical 11/1/2022 Partial Approval JOSE AVILA
Drywall Nailing 11/9/2022 Partial Approval JOSE AVILA
Underground Mechanical 11/9/2022 Corrections Issued JOSE AVILA
Underground Mechanical 11/23/2022 Not Ready for Inspection BRENDAN MORELLI
Drywall Nailing 11/30/2022 Approved JOSE AVILA
Underground Mechanical 11/30/2022 Partial Approval JOSE AVILA
ELECTRICAL-Final 12/23/2022 Corrections Issued JOSE AVILA
Final 12/23/2022 Corrections Issued JOSE AVILA
Green Building Final 12/23/2022 Approved JOSE AVILA
HVAC-Final 12/23/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 12/23/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/23/2022 SGSOV Not Ready JOSE AVILA
Smoke Detectors 12/23/2022 Approved JOSE AVILA
ELECTRICAL-Final 12/28/2022 Approved JOSE AVILA
HVAC-Final 12/28/2022 Approved JOSE AVILA
PLUMBING-Final 12/28/2022 Approved JOSE AVILA
Final 1/19/2023 Partial Approval JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/19/2023 SGSOV Approved JOSE AVILA
Service/Power Release 1/19/2023 Approved JOSE AVILA