739 N NORTH MAIN ST 90012
Certificate Information: 739 N NORTH MAIN ST 90012
- Application / Permit
- 21016-10000-51559
- Plan Check / Job No.
- B21LA20945
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Change of use from restaurant to office.
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- CofO Issued on 12/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2021 | ZAW HAN |
| Corrections Issued | 11/9/2021 | ZAW HAN |
| Applicant returned to address corrections | 11/17/2021 | ZAW HAN |
| Applicant returned to address corrections | 1/24/2022 | ZAW HAN |
| Plan Check Approved | 3/20/2022 | JOE VO |
| Issued | 3/23/2022 | APPLICANT |
| CofO in Progress | 12/7/2023 | RAMAZANALI ALMASI |
| CofO Issued | 12/12/2023 | ERNESTO CORRAL |
| Permit Finaled | 12/12/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/1/2021 | CELINA MORENO |
| Sewer availability | Cleared | 12/1/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2021 | CELINA MORENO |
| Redevelopment Project Area | Cleared | 2/18/2022 | GRACIELA ACOSTA |
| Internal circulation | Cleared | 2/23/2022 | KEVIN ARUCAN |
| DAS Clearance | Cleared | 3/20/2022 | JOE VO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 8/30/2023 | Corrections Issued | JULIAN CAPUCETTI |
| Reinforced Masonry Frame | 8/30/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| SGSOV-Seismic Gas S/O Valve | 8/30/2023 | SGSOV Approved | JULIAN CAPUCETTI |
| Smoke Detectors | 8/30/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| Final | 9/12/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Reinforced Masonry Frame | 9/12/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Smoke Detectors | 9/12/2023 | Approved | RAFAEL CORTES |
| Final | 10/10/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Reinforced Masonry Frame | 10/10/2023 | Approved | RAFAEL CORTES |
| Final | 10/25/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 11/9/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 11/14/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Special/Order Compliance | 11/14/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 11/15/2023 | Partial Inspection | RAMAZANALI ALMASI |
| Final | 11/17/2023 | Conditional Approval | RAMAZANALI ALMASI |