5132 E CORINGA DR 90042

Certificate Information: 5132 E CORINGA DR 90042

Application / Permit
21016-10000-51270
Plan Check / Job No.
B21LA20851
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE/STORAGE BLDG. INTO A.D.U. PER LAMC 12.22 A.33(c)-(d)
Permit Issued
Issued on 8/24/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2021 APPLICANT
Assigned to Plan Check Engineer 11/15/2021 LAWRENCE QUIRANTE
Corrections Issued 11/16/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 6/3/2022 SAMUEL GONZALEZ
Plan Check Approved 7/15/2022 RAHEL BEYENE
Issued 8/24/2022 APPLICANT
CofO in Progress 7/25/2023 CRAIG VAUGHAN
CofO in Progress 7/25/2023 CRAIG VAUGHAN
CofO Issued 7/26/2023 DEROLD HAUFF
Permit Finaled 7/26/2023 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 3/11/2022 CELINA MORENO
Address approval Cleared 6/6/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 7/11/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 1/26/2023 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 1/26/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 2/17/2023 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 2/17/2023 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 2/23/2023 Approved SCOTT FINNILA
ELECTRICAL-Rough 2/23/2023 Approved SCOTT FINNILA
Green Building Rough 2/23/2023 Approved SCOTT FINNILA
HVAC-Rough 2/23/2023 Approved SCOTT FINNILA
PLUMBING-Rough 2/23/2023 Approved SCOTT FINNILA
Insulation 2/27/2023 Approved CHARLES BOGHOSKHAN
Drywall Nailing 3/2/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 3/2/2023 Corrections Issued KATHRYN BUTTERWORTH
Interior/Exterior Lathing 3/9/2023 Approved OSVALDO PARAMO
Sewer 4/4/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 5/24/2023 Not Ready for Inspection CRAIG VAUGHAN
Final 5/24/2023 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 5/24/2023 Approved CRAIG VAUGHAN
HVAC-Final 5/24/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 5/24/2023 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/24/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 5/24/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 5/31/2023 Corrections Issued CRAIG VAUGHAN
Final 5/31/2023 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 5/31/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 5/31/2023 Approved CRAIG VAUGHAN
Smoke Detectors 5/31/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 7/10/2023 Not Ready for Inspection CRAIG VAUGHAN
Final 7/10/2023 Not Ready for Inspection CRAIG VAUGHAN
Final 7/24/2023 OK to Issue CofO KATHRYN BUTTERWORTH