330 1/2 N CROFT AVE 90048
Certificate Information: 330 1/2 N CROFT AVE 90048
- Application / Permit
- 21016-10000-50280
- Plan Check / Job No.
- B21LA20714
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 561 SQ. FT. (E) ONE STORY 4-CAR DETACHED GARAGE TO (N) ADU (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 4/19/2022
- Issuing Office
- Current Status
- CofO Issued on 3/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 11/10/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 1/7/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 2/21/2022 | AUNG SOE |
| Applicant returned to address corrections | 3/10/2022 | TSE MING HUANG |
| Plan Check Approved | 4/14/2022 | CHRISTOPHER KOMANCHECK |
| Issued | 4/19/2022 | APPLICANT |
| Building Plans Picked Up | 4/22/2022 | APPLICANT |
| CofO in Progress | 3/20/2025 | JOSE MACIAS |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
| CofO Issued | 3/20/2025 | DEROLD HAUFF |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2021 | THOMAS LANG |
| Sewer availability | Cleared | 11/20/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 2/15/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sin,, John P; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2023 | Partial Inspection | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 3/19/2024 | Approved | AMIR NAZARIAN |
| Footing/Foundation/Slab | 3/21/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 4/12/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 4/19/2024 | Partial Approval | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 5/21/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 5/21/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Rough | 5/21/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 5/21/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 6/4/2024 | Conditional Approval | AMIR NAZARIAN |
| PLUMBING-Rough | 6/4/2024 | Conditional Approval | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 6/14/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 6/14/2024 | Conditional Approval | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 6/20/2024 | No Access for Inspection | AMIR NAZARIAN |
| METHANE-Rough | 6/20/2024 | No Access for Inspection | AMIR NAZARIAN |
| Special/Order Compliance | 6/20/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Sewer | 9/16/2024 | Corrections Issued | JOSE MACIAS |
| Drywall Nailing | 10/3/2024 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 10/3/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 10/3/2024 | Corrections Issued | JOSE MACIAS |
| Sewer | 10/3/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 10/4/2024 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/4/2024 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/4/2024 | Partial Approval | ENRIQUE MIRELES |
| Drywall Nailing | 10/7/2024 | Not Ready for Inspection | JOSE MACIAS |
| Sewer | 10/7/2024 | Not Ready for Inspection | JOSE MACIAS |
| BUILDING-Rough-Frame | 10/11/2024 | Corrections Issued | JOSE MACIAS |
| Drywall Nailing | 10/11/2024 | Approved | JOSE MACIAS |
| Insulation | 10/11/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 10/11/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 10/18/2024 | Partial Approval | JOAQUIN GREENOUGH |
| Pre-Inspection | 10/18/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 10/25/2024 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/31/2024 | Partial Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 10/31/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Special/Order Compliance | 11/18/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/11/2024 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 12/11/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 12/18/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Shower Pan | 12/18/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Sewer | 12/24/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 1/6/2025 | Not Ready for Inspection | JOSE MACIAS |
| Shower Pan | 1/6/2025 | Not Ready for Inspection | JOSE MACIAS |
| Interior/Exterior Lathing | 1/13/2025 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 1/13/2025 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/21/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 2/21/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Final | 2/21/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 2/21/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 2/21/2025 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 2/21/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/26/2025 | No Access for Inspection | JOAQUIN GREENOUGH |
| Final | 2/26/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| METHANE-Final | 2/26/2025 | No Access for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 2/26/2025 | No Access for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 2/26/2025 | No Access for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/11/2025 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 3/11/2025 | Approved | JOAQUIN GREENOUGH |
| Final | 3/11/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Final | 3/11/2025 | Approved | JOAQUIN GREENOUGH |
| METHANE-Final | 3/11/2025 | Approved | JOAQUIN GREENOUGH |
| METHANE-Rough | 3/11/2025 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 3/11/2025 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 3/11/2025 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 3/19/2025 | Approved | JOSE MACIAS |
| Final | 3/19/2025 | OK to Issue CofO | JOSE MACIAS |
| HVAC-Final | 3/19/2025 | Approved | JOSE MACIAS |
| PLUMBING-Final | 3/19/2025 | Approved | JOSE MACIAS |
| Service/Power Release | 3/19/2025 | Approved | JOSE MACIAS |