11301 W CAMARILLO ST 91602

Certificate Information: 11301 W CAMARILLO ST 91602

Application / Permit
21016-10000-49587
Plan Check / Job No.
B21LA20523
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Gymnasium
Work Description
CHANGE OF USE FROM OFFICE TO PILATES STUDIO
Permit Issued
Issued on 5/4/2022
Issuing Office
Current Status
CofO Issued on 3/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 HERNAN ARREOLA
Corrections Issued 12/23/2021 HERNAN ARREOLA
Quality Review Completed 12/29/2021 TEODORO DIAZ RODRIGUEZ
Disabled Access Plans Picked Up 2/1/2022 APPLICANT
Green Plans Picked Up 2/7/2022 APPLICANT
Applicant returned to address corrections 4/4/2022 HERNAN ARREOLA
Plan Check Approved 5/4/2022 HERNAN ARREOLA
Issued 5/4/2022 APPLICANT
CofO in Progress 3/23/2023 ROBERT DAVIS
CofO Issued 3/23/2023 JEFFREY DURAN
Permit Finaled 3/23/2023 JEFFREY DURAN

Permit Application Clearance Information

Green Code Cleared 12/28/2021 AARON COSTA
Eng Process Fee Ord 176,300 Cleared 4/14/2022 CARLOS AGUILERA
Sewer availability Cleared 4/14/2022 CARLOS AGUILERA
DAS Clearance Cleared 4/20/2022 HERNAN ARREOLA

Contact Information

Contractor D R N Sterling Construction Inc; Lic. No.: 959541-B 323 SOUTH DOHENY DR 103      LOS ANGELES, CA 90048

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 7/18/2022 Not Ready for Inspection ROBERT DAVIS
Wood Frame 9/9/2022 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 10/7/2022 Approved ROBERT DAVIS
Drywall Nailing 10/17/2022 Approved ROBERT DAVIS
Insulation 10/17/2022 Approved ROBERT DAVIS
Drywall Nailing 10/20/2022 Approved ROBERT DAVIS
Final 12/22/2022 Corrections Issued ANDREW DORSO
Green Building Final 12/22/2022 Not Ready for Inspection ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Not Ready ANDREW DORSO
Smoke Detectors 12/22/2022 Not Ready for Inspection ANDREW DORSO
Final 2/27/2023 Corrections Issued ROBERT DAVIS
Green Building Final 2/27/2023 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved ROBERT DAVIS
Smoke Detectors 2/27/2023 Approved ROBERT DAVIS
Special/Order Compliance 2/27/2023 Not Ready for Inspection STEVEN LEVITT
Final 3/14/2023 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 3/17/2023 Partial Approval ROBERT DAVIS
Final 3/22/2023 OK to Issue CofO ROBERT DAVIS