5919 N CANOGA AVE 91367

Certificate Information: 5919 N CANOGA AVE 91367

Application / Permit
21016-10000-48225
Plan Check / Job No.
B21LA20431
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Addition, interior and exterior alteration to existing restaurant and outdoor eating/dining area.
Permit Issued
Issued on 9/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 SALVADOR QUINTANILLA
Corrections Issued 12/1/2021 SALVADOR QUINTANILLA
Quality Review Completed 12/1/2021 PETER KIM
Building Plans Picked Up 12/3/2021 APPLICANT
Disabled Access Plans Picked Up 12/3/2021 APPLICANT
Applicant returned to address corrections 5/11/2022 SALVADOR QUINTANILLA
Applicant returned to address corrections 6/1/2022 SALVADOR QUINTANILLA
Applicant returned to address corrections 6/2/2022 SALVADOR QUINTANILLA
Applicant returned to address corrections 6/9/2022 SALVADOR QUINTANILLA
Applicant returned to address corrections 6/14/2022 SALVADOR QUINTANILLA
Applicant returned to address corrections 8/16/2022 SALVADOR QUINTANILLA
Plan Check Approved 9/26/2022 SALVADOR QUINTANILLA
Issued 9/28/2022 APPLICANT
TCO Issued (Expire Date: 05-19-2024) 11/21/2023 JEFFREY DURAN
CofO in Progress 3/4/2024 CAMERON CHABAN
Permit Finaled 3/8/2024 RICKEY JACKSON
CofO Issued 3/8/2024 RICKEY JACKSON
Permit Finaled 3/8/2024 RICKEY JACKSON

Permit Application Clearance Information

ZA Case Cleared 12/8/2021 PABLO ESTRADA
ZA Case Cleared 12/8/2021 PABLO ESTRADA
ZA Case Cleared 12/8/2021 PABLO ESTRADA
ZA Case Cleared 12/8/2021 PABLO ESTRADA
Green Code Cleared 1/5/2022 SALVADOR QUINTANILLA
Fire Marshal Fire Life Safety Cleared 1/31/2022 ANDREW KO
Food Service Establishment Cleared 3/7/2022 KENNETH BROWNE
DAS Clearance Cleared 3/31/2022 SHINE LIN
Eng Process Fee Ord 176,300 Cleared 4/1/2022 CARLOS AGUILERA
Highway dedication Cleared 4/1/2022 CARLOS AGUILERA
Sewer availability Cleared 4/1/2022 CARLOS AGUILERA
Food establishment approval Cleared 6/1/2022 LACDHS APPROVED
Low Impact Development Cleared 7/12/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/20/2022 LEE GUILBEAUX
ZA Case Cleared 7/21/2022 RICARDO MARTINEZ
Miscellaneous Cleared 7/27/2022 LOUIS ORTEGA
Specific Plan Cleared 9/19/2022 MIGUEL GAMBOA

Contact Information

Contractor P R Construction Inc; Lic. No.: 673267-B 1995 BATAVIA STREET      ORANGE, CA 92865
Engineer Impson,, David Franklin; Lic. No.: C73590 26 LOTUS CT      GREENVILLE, SC 29609

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/12/2022 Not Ready for Inspection JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/27/2022 Partial Inspection BRIAN KELLY
Footing/Foundation/Slab 2/16/2023 Approved BRIAN KELLY
Pre-Inspection 3/6/2023 Approved BRIAN KELLY
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Partial Inspection BRIAN KELLY
Deputy Drilled-In Anchors 4/13/2023 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 4/13/2023 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 4/14/2023 Conditional Approval BRIAN KELLY
Green Building Rough 4/14/2023 Partial Inspection BRIAN KELLY
Wood Frame 4/14/2023 Partial Approval BRIAN KELLY
Deputy Steel/Welding 4/17/2023 Conditional Approval BRIAN KELLY
Drywall Nailing 4/19/2023 Partial Approval BRIAN KELLY
Excavation/Setback/Form/Re-Bar 5/1/2023 Partial Approval BRIAN KELLY
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Partial Inspection BRIAN KELLY
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval BRIAN KELLY
Green Building Rough 5/11/2023 Partial Approval BRIAN KELLY
Structural Steel Frame 5/11/2023 Not Ready for Inspection BRIAN KELLY
Wall Anchors 5/11/2023 Partial Approval BRIAN KELLY
Wood Frame 5/11/2023 Partial Approval BRIAN KELLY
Floor/Roof Diaphrgm/Shear Wall 5/16/2023 Partial Approval BRIAN KELLY
Structural Steel Frame 5/16/2023 Not Ready for Inspection BRIAN KELLY
Deputy Wood Construction 5/19/2023 Conditional Approval BRIAN KELLY
Drywall Nailing 5/22/2023 Partial Approval BRIAN KELLY
Insulation 5/22/2023 Partial Approval BRIAN KELLY
Drywall Nailing 5/24/2023 Partial Approval BRIAN KELLY
Structural Steel Frame 5/24/2023 Partial Approval BRIAN KELLY
Deputy Reinf. Concrete 5/25/2023 Conditional Approval BRIAN KELLY
Drywall Nailing 5/31/2023 Partial Approval BRIAN KELLY
Wall Anchors 5/31/2023 Approved BRIAN KELLY
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Partial Approval BRIAN KELLY
Light Gage Steel Frame 6/14/2023 Partial Approval BRIAN KELLY
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval BRIAN KELLY
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Partial Approval BRIAN KELLY
T-Bar Ceiling 7/17/2023 Partial Approval BRIAN KELLY
T-Bar Ceiling 7/28/2023 Approved BRIAN KELLY
Drywall Nailing 8/7/2023 Partial Approval BRIAN KELLY
Drywall Nailing 8/11/2023 Partial Approval BRIAN KELLY
Excavation/Setback/Form/Re-Bar 8/18/2023 Approved BRIAN KELLY
Final 9/7/2023 Partial Inspection DANIEL VARNUM
Green Building Final 9/7/2023 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 9/7/2023 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 9/7/2023 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 9/7/2023 Not Ready for Inspection DANIEL VARNUM
Wood Frame 9/7/2023 Not Ready for Inspection DANIEL VARNUM
Green Building Final 10/10/2023 Partial Inspection CAMERON CHABAN
Final 10/11/2023 Off-Hour Fees Due
Green Building Rough 10/11/2023 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 10/11/2023 Off-Hour Fees Due
Smoke Detectors 10/11/2023 Off-Hour Fees Due
Wood Frame 10/11/2023 Off-Hour Fees Due
Green Building Final 10/30/2023 Partial Inspection CAMERON CHABAN
Final 11/15/2023 Partial Inspection CAMERON CHABAN
Green Building Final 11/15/2023 Approved CAMERON CHABAN
Green Building Rough 11/15/2023 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Approved CAMERON CHABAN
Smoke Detectors 11/15/2023 Approved CAMERON CHABAN
Wood Frame 11/15/2023 Approved CAMERON CHABAN
Final 11/21/2023 OK for TCO CAMERON CHABAN
Final 3/4/2024 OK to Issue CofO CAMERON CHABAN