2002 S VINEYARD AVE 1-7 90016

Certificate Information: 2002 S VINEYARD AVE 1-7 90016

Application / Permit
21016-10000-48207
Plan Check / Job No.
B21LA20421
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) ATTACHED GARAGE OF A 2 STORY 6 UNIT APARTMENT INTO AN ADU PER GCS 65852.2(e)(1)(C) AT REAR OF BLDG.
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
CofO Issued on 1/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 LUKE GONZALES
Corrections Issued 11/4/2021 LUKE GONZALES
Issued 2/9/2022 APPLICANT
Building Plans Picked Up 2/16/2022 APPLICANT
CofO in Progress 11/27/2023 ALFREDO LOPEZ
Permit Finaled 1/17/2024 ERNESTO CORRAL
CofO Issued 1/17/2024 ERNESTO CORRAL
Permit Finaled 1/17/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 11/12/2021 CINDY QI
Sewer availability Cleared 11/12/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 11/15/2021 CINDY QI
Tenant Habitability Plan Cleared 12/9/2021 MICHAEL SOTO

Contact Information

Contractor Jerahian Araz; Lic. No.: 1045340-B 250 N COLLEGE PARK DR F36      UPLAND, CA 91786
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

ALFREDO LOPEZ, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/10/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 6/30/2022 Conditional Approval DARRYL ARNOLD
Wood Frame 8/8/2022 No Access for Inspection EDWIN GREGORYONA
Wood Frame 8/12/2022 Partial Inspection RUSSELL BONVOULOIR
Pre-Inspection 8/17/2022 Corrections Issued RUSSELL BONVOULOIR
Green Building Rough 9/8/2022 Approved TIMOTHY BUXTON
Wood Frame 9/8/2022 Approved TIMOTHY BUXTON
Insulation 9/13/2022 Partial Inspection KATY RAMIREZ
Interior/Exterior Lathing 9/15/2022 Not Ready for Inspection KATY RAMIREZ
Insulation 9/16/2022 Partial Approval KATY RAMIREZ
Interior/Exterior Lathing 9/16/2022 Partial Approval KATY RAMIREZ
Wood Frame 9/16/2022 Partial Inspection KATY RAMIREZ
Drywall Nailing 10/7/2022 Approved GREGORY POMISH
Green Building Final 6/16/2023 Not Ready for Inspection ALFREDO LOPEZ
Final 6/29/2023 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 6/29/2023 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 6/29/2023 Not Ready for Inspection ALFREDO LOPEZ
Final 9/6/2023 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 9/6/2023 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 9/6/2023 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 9/6/2023 Approved ALFREDO LOPEZ
Final 10/16/2023 Conditional Approval VAHE KELEDJIAN
Green Building Final 10/16/2023 Approved VAHE KELEDJIAN
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Approved VAHE KELEDJIAN
Final 11/17/2023 Corrections Issued DARRYL ARNOLD
Final 11/22/2023 Partial Approval RICARDO ROBLES