1507-1509 E 53RD ST 90011
Certificate Information: 1507-1509 E 53RD ST 90011
- Application / Permit
- 21016-10000-48062
- Plan Check / Job No.
- B21LA20376
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- REMODEL TO CONVERT 4-UNIT APARTMENT INTO TWO-FAMILY DWELLING: REPLACE (11) DOORS AND (6) WINDOWS LIKE FOR LIKE.
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 3/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | JESSE JIMENEZ |
| Corrections Issued | 11/4/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 12/1/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 3/2/2022 | SHANGQIN XIE |
| Issued | 3/2/2022 | APPLICANT |
| Building Plans Picked Up | 3/3/2022 | APPLICANT |
| CofO in Progress | 2/28/2023 | BRENDAN MORELLI |
| Permit Finaled | 3/1/2023 | DEROLD HAUFF |
| CofO Issued | 3/1/2023 | DEROLD HAUFF |
| Permit Finaled | 3/1/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2021 | THAN WIN |
| Community Plan Implem. Overlay | Cleared | 1/11/2022 | HELEN JADALI |
| Demo/Removal of Rental Units | Cleared | 2/11/2022 | EVAN SMOLLER |
| Tenant Habitability Plan | Cleared | 2/23/2022 | PHILLIP MUNGUIA |
Contact Information
| Contractor | C C D L Investments Inc; Lic. No.: 906858-B | 205 AVENIDA DEL MAR #0896 SAN CLEMENTE, CA 92672 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/10/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/10/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/10/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/21/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/21/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/21/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/5/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 4/5/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/14/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 4/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/19/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 4/19/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/27/2022 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/6/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/12/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/12/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/2/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/2/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/22/2022 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 8/22/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 8/22/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 9/12/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Drywall Nailing | 9/20/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/17/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 10/21/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/7/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/2/2023 | Corrections Issued | BRENDAN MORELLI |
| Final | 2/2/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Final | 2/2/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 2/2/2023 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 2/2/2023 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 2/17/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/17/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 2/17/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 2/17/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/17/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/24/2023 | OK to Issue CofO | BRENDAN MORELLI |