677 W CYPRESS AVE 90065
Certificate Information: 677 W CYPRESS AVE 90065
- Application / Permit
- 21016-10000-48056
- Plan Check / Job No.
- B21LA20366
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2 STORY BUILDING, ADU OVER 2 CAR GARAGE. PER ORD 186,481
- Permit Issued
- Issued on 4/14/2023
- Issuing Office
- Current Status
- CofO Issued on 1/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2021 | HERNAN ARREOLA |
| Corrections Issued | 12/5/2021 | HERNAN ARREOLA |
| Quality Review Completed | 12/14/2021 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 11/21/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/30/2022 | HERNAN ARREOLA |
| Plan Check Approved | 4/10/2023 | HERNAN ARREOLA |
| No Progress | 4/10/2023 | HERNAN ARREOLA |
| Plan Check Approved | 4/10/2023 | HERNAN ARREOLA |
| Issued | 4/14/2023 | APPLICANT |
| CofO in Progress | 1/16/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 1/18/2025 | DEROLD HAUFF |
| CofO Issued | 1/18/2025 | DEROLD HAUFF |
| Permit Finaled | 1/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2022 | STEVE MELGAR |
| Low Impact Development | Cleared | 7/11/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 7/14/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 7/18/2022 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 7/19/2022 | KIRK LINKLATER |
| Construction near power lines | Cleared | 8/4/2022 | RIDWAN HARDY |
| Supp. Use District POD/CDO/TDO | Cleared | 10/31/2022 | NASHYA JENSEN |
| ZI | Cleared | 10/31/2022 | NASHYA JENSEN |
| GPI Written Notices | Cleared | 11/16/2022 | HERNAN ARREOLA |
Contact Information
| Contractor | Sarraf Contracting Inc; Lic. No.: 1074518-B | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/20/2023 | Approved | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/30/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 5/31/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/20/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 6/20/2023 | Partial Approval | OSVALDO PARAMO |
| Sewer | 6/20/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/21/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 6/21/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Underground Mechanical | 6/21/2023 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 8/3/2023 | Corrections Issued | BRIAN SULLIVAN |
| Wood Frame | 8/3/2023 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 8/8/2023 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/25/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 9/6/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 9/8/2023 | Partial Approval | OSVALDO PARAMO |
| Insulation | 9/14/2023 | Approved | JOSH MEISTER |
| Drywall Nailing | 9/21/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 9/21/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/21/2023 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/29/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/29/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/29/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 2/29/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 2/29/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/24/2024 | Corrections Issued | JOSEPH MCGARRY |
| Final | 7/1/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Final | 7/1/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Not Ready | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Final | 10/25/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 10/25/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/25/2024 | SGSOV Approved | OSVALDO PARAMO |
| Final | 1/15/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |