5846 1/2 S HOOVER ST 90044

Certificate Information: 5846 1/2 S HOOVER ST 90044

Application / Permit
21016-10000-48046
Plan Check / Job No.
B21LA20353
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO ACCESORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d), (1,200 SF max per Ordinance)
Permit Issued
Issued on 2/18/2022
Issuing Office
Current Status
CofO Issued on 1/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 SHANGQIN XIE
Corrections Issued 11/4/2021 SHANGQIN XIE
Applicant returned to address corrections 1/28/2022 ZAW HAN
Plan Check Approved 1/31/2022 ZAW HAN
Issued 2/18/2022 APPLICANT
Building Plans Picked Up 2/22/2022 APPLICANT
CofO in Progress 10/18/2022 SHAVONNE ESPINOZA
Permit Finaled 1/14/2023 DEROLD HAUFF
CofO Issued 1/14/2023 DEROLD HAUFF
Permit Finaled 1/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/13/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 11/16/2021 JOSE HERNANDEZ
Sewer availability Cleared 11/16/2021 JOSE HERNANDEZ
Community Plan Implem. Overlay Cleared 1/6/2022 RAFAEL FONTES
ZA Case Cleared 1/6/2022 RAFAEL FONTES
Construction near power lines Cleared 1/13/2022 WALTER RAMIREZ

Contact Information

Contractor New World Construction; Lic. No.: 864461-B 838 E 93RD STREET      LOS ANGELES, CA 90002
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2022 Partial Approval JOAQUIN GREENOUGH
PLUMBING-Rough 3/30/2022 Partial Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 4/11/2022 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 4/11/2022 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 4/15/2022 Approved HORACE FULTZ
Excavation/Setback/Form/Re-Bar 4/18/2022 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/17/2022 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 5/17/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/20/2022 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 5/20/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 5/20/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/13/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 6/13/2022 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 6/13/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 6/13/2022 Approved JOAQUIN GREENOUGH
Insulation 6/22/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 6/22/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 7/5/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 7/5/2022 Approved ALIZAH MAYAGOITIA
Final 9/19/2022 Corrections Issued SHAVONNE ESPINOZA
Green Building Final 9/19/2022 Corrections Issued SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Not Ready SHAVONNE ESPINOZA
Smoke Detectors 9/19/2022 Approved SHAVONNE ESPINOZA
ELECTRICAL-Rough 9/22/2022 Partial Inspection SHAVONNE ESPINOZA
ELECTRICAL-Rough 9/28/2022 Corrections Issued SHAVONNE ESPINOZA
Final 9/28/2022 Corrections Issued SHAVONNE ESPINOZA
Green Building Final 9/28/2022 Corrections Issued SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Approved SHAVONNE ESPINOZA
ELECTRICAL-Final 10/6/2022 Approved SHAVONNE ESPINOZA
ELECTRICAL-Rough 10/6/2022 Approved SHAVONNE ESPINOZA
Final 10/6/2022 Conditional Approval SHAVONNE ESPINOZA
Green Building Final 10/6/2022 Approved SHAVONNE ESPINOZA
HVAC-Final 10/6/2022 Approved SHAVONNE ESPINOZA
PLUMBING-Final 10/6/2022 Approved SHAVONNE ESPINOZA
Final 10/17/2022 OK to Issue CofO SHAVONNE ESPINOZA
Special/Order Compliance 10/17/2022 Approved SHAVONNE ESPINOZA