4332 N EAGLE ROCK BLVD 90041

Certificate Information: 4332 N EAGLE ROCK BLVD 90041

Application / Permit
21016-10000-48045
Plan Check / Job No.
B21LA20350
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE (PORTION OF RETAIL SPACE TO RESTAURANT) T.I. (NO STRUCTURAL CHANGE), ADA BATHROOM, COMMERICAL FLOORING, SINKS, TAKE OUT WINDOW. Hours of operation will be from 7:00 am to 11 pm.
Permit Issued
Issued on 12/9/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 LAWRENCE QUIRANTE
Corrections Issued 12/6/2021 SALVADOR QUINTANILLA
Building Plans Picked Up 12/14/2021 APPLICANT
Disabled Access Plans Picked Up 2/2/2022 APPLICANT
Quality Review Completed 11/17/2022 PETER KIM
Plan Check Approved 12/9/2022 SALVADOR QUINTANILLA
Issued 12/9/2022 APPLICANT
CofO in Progress 8/19/2024 RAMAZANALI ALMASI
CofO Issued 8/20/2024 ERNESTO CORRAL
Permit Finaled 8/20/2024 ERNESTO CORRAL

Permit Application Clearance Information

Food establishment approval Cleared 12/8/2021 LACDHS APPROVED
"Q" conditions Cleared 4/13/2022 KENTON TRINH
Comm Cor/Mini-Mall Cleared 4/13/2022 KENTON TRINH
Miscellaneous Cleared 4/13/2022 KENTON TRINH
Tract Map conditions Cleared 4/13/2022 KENTON TRINH
ZA Case Cleared 4/13/2022 KENTON TRINH
Supp. Use District POD/CDO/TDO Cleared 4/28/2022 NASHYA JENSEN
Eng Process Fee Ord 176,300 Cleared 5/20/2022 AMAAN MALIK
Sewer availability Cleared 5/20/2022 AMAAN MALIK
Food Service Establishment Cleared 7/8/2022 RAMESHBHAIR PATEL
DAS Clearance Cleared 11/2/2022 EDDIE GARIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 12/22/2023 Not Ready for Inspection RAFAEL CORTES
Wood Frame 1/8/2024 Conditional Approval RAMAZANALI ALMASI
Drywall Nailing 1/11/2024 Approved RAMAZANALI ALMASI
Final 8/6/2024 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 8/6/2024 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 8/6/2024 Approved RAMAZANALI ALMASI
Final 8/14/2024 Conditional Approval RAMAZANALI ALMASI
Final 8/19/2024 OK to Issue CofO RAMAZANALI ALMASI