3807-3809 W 6TH ST 90020

Certificate Information: 3807-3809 W 6TH ST 90020

Application / Permit
21016-10000-47533
Plan Check / Job No.
B21LA20238
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Combine two tenant spaces to change the use of both from an ice cream parlor & retail to ceate a restaurant. Add rooftop platforms for new equipment.
Permit Issued
Issued on 4/1/2022
Issuing Office
Current Status
CofO Issued on 11/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2021 APPLICANT
Assigned to Plan Check Engineer 11/3/2021 SAMUEL GONZALEZ
Corrections Issued 11/4/2021 SAMUEL GONZALEZ
Plan Check Approved 2/2/2022 RICARDO RAMIREZ
Issued 4/1/2022 APPLICANT
Building Plans Picked Up 4/4/2022 APPLICANT
CofO in Progress 11/16/2022 KATY RAMIREZ
CofO Issued 11/22/2022 ERNESTO CORRAL
Permit Finaled 11/22/2022 ERNESTO CORRAL

Permit Application Clearance Information

Historic Resource Verification Cleared 12/17/2021 MAX LODER
Food Service Establishment Cleared 12/22/2021 JASH PATEL
Redevelopment Project Area Cleared 12/22/2021 DAVID URITA
Sewer availability Cleared 1/13/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/20/2022 TREVOR QUAN
Food establishment approval Cleared 2/2/2022 LACDHS APPROVED

Contact Information

Architect Kil,, Andrew Han; Lic. No.: C31817 13005 MESA VERDE WAY      SYLMAR, CA 91342
Contractor Shin Jae W; Lic. No.: 1037181-B 1011 S SERRANO AVENUE #104      LOS ANGELES, CA 90006
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/25/2022 Partial Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 6/23/2022 Corrections Issued NICK DANERI
Wood Frame 6/23/2022 Partial Approval NICK DANERI
Drywall Nailing 7/5/2022 Approved JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 7/18/2022 Approved JONATHAN QUACH
T-Bar Ceiling 10/5/2022 Approved JONATHAN QUACH
Final 11/8/2022 Partial Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved KATY RAMIREZ
Smoke Detectors 11/8/2022 Approved KATY RAMIREZ
Final 11/17/2022 OK to Issue CofO KATY RAMIREZ