6423 S HAAS AVE 90047

Certificate Information: 6423 S HAAS AVE 90047

Application / Permit
21016-10000-47515
Plan Check / Job No.
B21LA20223
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Covert existing part of garage into an ADU.
Permit Issued
Issued on 12/7/2021
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2021 APPLICANT
Assigned to Plan Check Engineer 11/1/2021 JOE VO
Corrections Issued 11/2/2021 JOE VO
Plan Check Approved 11/30/2021 JOE VO
Issued 12/7/2021 APPLICANT
CofO in Progress 8/5/2022 ENRIQUE MIRELES
Permit Finaled 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/19/2021 ABEL CASILLAS
Sewer availability Cleared 11/19/2021 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 11/22/2021 ABEL CASILLAS

Contact Information

Contractor Villalobos B M Inc; Lic. No.: 872939-B 11606 WASHINGTON BLVD UNIT D      WHITTIER, CA 90606

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/30/2021 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 12/30/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 12/30/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 12/30/2021 Corrections Issued FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 12/30/2021 Not Ready for Inspection FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 1/7/2022 Partial Approval HORACE FULTZ
Wood Frame 1/7/2022 Approved HORACE FULTZ
Rough-Elec/Plmb/HVAC 1/31/2022 Corrections Issued FREDDIE RIVERA
Wood Frame 1/31/2022 Approved FREDDIE RIVERA
HVAC-Rough 3/23/2022 Approved ENRIQUE MIRELES
Insulation 3/31/2022 Approved ENRIQUE MIRELES
Drywall Nailing 4/6/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 7/14/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 7/14/2022 Approved ENRIQUE MIRELES
Final 7/14/2022 Corrections Issued ENRIQUE MIRELES
PLUMBING-Final 7/14/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/14/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 7/14/2022 Approved ENRIQUE MIRELES
Final 7/29/2022 Corrections Issued JOAQUIN GREENOUGH