3041 S VINEYARD AVE 90016
Certificate Information: 3041 S VINEYARD AVE 90016
- Application / Permit
- 21016-10000-47265
- Plan Check / Job No.
- B21LA20150
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/25/2022
- Issuing Office
- Current Status
- CofO Issued on 10/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2021 | DANIEL SANJUAN |
| Corrections Issued | 10/30/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 2/9/2022 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 2/11/2022 | APPLICANT |
| Plan Check Approved | 2/23/2022 | SERGIO GUTIERREZ |
| Issued | 2/25/2022 | APPLICANT |
| CofO in Progress | 10/16/2025 | JUSTIN HAWLEY |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
| CofO Issued | 10/17/2025 | DEROLD HAUFF |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2021 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 11/19/2021 | CINDY QI |
| Sewer availability | Cleared | 11/19/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2021 | CINDY QI |
| Flood clearance | Cleared | 2/1/2022 | TIFFANY WONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Banning,, George Kwame; Lic. No.: C53074 | 7550 LILY COURT FONTANA, CA 92336 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/3/2022 | Approved | SHAVONNE ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 3/4/2022 | Corrections Issued | RUBEN SALAS |
| Pre-Inspection | 3/4/2022 | Not Ready for Inspection | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 3/9/2022 | Corrections Issued | STUART CHAPMAN |
| FLOOD-Elevation Certificate | 3/9/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/9/2022 | Corrections Issued | STUART CHAPMAN |
| Sewer | 3/24/2022 | Corrections Issued | STUART CHAPMAN |
| FLOOD-Elevation Certificate | 3/30/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Partial Approval | STUART CHAPMAN |
| Sewer | 3/30/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 3/30/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/29/2022 | No Access for Inspection | STUART CHAPMAN |
| HVAC-Rough | 4/29/2022 | No Access for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 4/29/2022 | No Access for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 5/2/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 5/2/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 5/2/2022 | Approved | STUART CHAPMAN |
| Deputy Wood Construction | 5/5/2022 | Conditional Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/24/2022 | No Access for Inspection | SCOTT FINNILA |
| Drywall Nailing | 5/24/2022 | No Access for Inspection | SCOTT FINNILA |
| FLOOD-Proofing Certificate | 5/24/2022 | No Access for Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2022 | No Access for Inspection | SCOTT FINNILA |
| Green Building Rough | 5/24/2022 | No Access for Inspection | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/24/2022 | No Access for Inspection | SCOTT FINNILA |
| Wood Frame | 5/24/2022 | No Access for Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 5/27/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 5/27/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/27/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 6/7/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 6/23/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 10/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 10/27/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/27/2022 | Approved | STUART CHAPMAN |
| Green Building Final | 10/27/2022 | Approved | STUART CHAPMAN |
| HVAC-Final | 10/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 10/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 10/27/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 12/1/2022 | Corrections Issued | BRENDAN MORELLI |
| Final | 12/1/2022 | Partial Approval | BRENDAN MORELLI |
| HVAC-Final | 12/1/2022 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Final | 12/1/2022 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 2/27/2023 | No Access for Inspection | CALEB MEISTER |
| Final | 2/27/2023 | Corrections Issued | CALEB MEISTER |
| HVAC-Final | 2/27/2023 | No Access for Inspection | CALEB MEISTER |
| PLUMBING-Final | 2/27/2023 | No Access for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 4/21/2023 | Approved | STUART CHAPMAN |
| Final | 4/21/2023 | Conditional Approval | STUART CHAPMAN |
| HVAC-Final | 4/21/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 4/21/2023 | Approved | STUART CHAPMAN |
| Final | 9/2/2025 | Corrections Issued | JUSTIN HAWLEY |
| Final | 9/3/2025 | OK to Expire Permit | JUSTIN HAWLEY |
| Final | 10/14/2025 | No Access for Inspection | JUSTIN HAWLEY |
| Final | 10/16/2025 | OK to Issue CofO | JUSTIN HAWLEY |