6415 W 87TH PL 90045

Certificate Information: 6415 W 87TH PL 90045

Application / Permit
21016-10000-47227
Plan Check / Job No.
B21LA20142
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) BEDROOM, CLOSET, LIVING ROOM AND KITCHEN. EXISTING ROOF. 1 ST STORY, 636 SF, TO BE RE-BUILDING AND NEW CEILING CATHEDRAL. EXISTING BEDROOM AND BATHROOM, 2ND STORY TO BE REMODELED. (E) FIRE PLACE TO BE DEMOED.
Permit Issued
Issued on 5/4/2022
Issuing Office
Current Status
Issued on 5/4/2022

Permit Application Status History

Submitted 11/3/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 CRYSTEL MAALOUF
Corrections Issued 11/29/2021 CRYSTEL MAALOUF
Quality Review Completed 12/10/2021 KEN GILL
Plan Check Approved 3/24/2022 CRYSTEL MAALOUF
Issued 5/4/2022 APPLICANT
Building Plans Picked Up 5/11/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/19/2022 JEANETTE VONG
CPC Cleared 1/28/2022 ANACANY HURTADO
Sewer availability Cleared 2/9/2022 ANTHONY MAINEZ
Specific Plan Cleared 2/25/2022 PEDRO AYALA
Hydrant and Access approval Cleared 3/8/2022 CINDY JOSSELYN

Contact Information

Contractor J & D Grand Construction Corp; Lic. No.: 979104-B 7508 3RD STREET      DOWNEY, CA 90241
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 5/18/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 5/18/2022 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Approved BOBBY KEY
Footing/Foundation/Slab 5/23/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/2/2022 Approved BOBBY KEY
Interior/Exterior Lathing 6/2/2022 Partial Approval BOBBY KEY
Insulation 6/6/2022 Corrections Issued RICHARD STEINBACH
Insulation 6/8/2022 Approved BOBBY KEY
Interior/Exterior Lathing 6/8/2022 Partial Approval BOBBY KEY
Wood Frame 6/8/2022 Approved BOBBY KEY
Drywall Nailing 6/21/2022 Approved BOBBY KEY
Interior/Exterior Lathing 6/29/2022 Approved BOBBY KEY
Final 2/9/2023 Corrections Issued BOBBY KEY
Final 2/22/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 2/22/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 2/22/2023 Approved HERBERT GIRON
Final 2/24/2023 Corrections Issued JESUS RODRIGUEZ
Special/Order Compliance 2/24/2023 Not Ready for Inspection JESUS RODRIGUEZ