3976 S EAST BLVD 90066
Certificate Information: 3976 S EAST BLVD 90066
- Application / Permit
- 21016-10000-46540
- Plan Check / Job No.
- B21LA20006
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (E) 2 Story SFD and create additional bedroom within existing space.
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/21/2023
Permit Application Status History
| Submitted | 10/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | HERNAN ARREOLA |
| Corrections Issued | 1/18/2022 | HERNAN ARREOLA |
| Plan Check Approved | 3/9/2022 | HERNAN ARREOLA |
| Issued | 3/9/2022 | APPLICANT |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Permit Finaled | 7/21/2023 | JESUS RODRIGUEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2022 | DINAH GARIN |
| Sewer availability | Cleared | 1/27/2022 | DINAH GARIN |
Contact Information
| Contractor | Klein Construction; Lic. No.: 891079-B | 13858 CHANDLER BLVD SHERMAN OAKS, CA 91401 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/19/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/19/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/14/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/14/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/14/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/16/2023 | Partial Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/24/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 3/24/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/24/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 3/24/2023 | Approved | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 3/30/2023 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/31/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/31/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 4/7/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/12/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Approved | HERBERT GIRON |
| Insulation | 4/12/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 4/20/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 7/21/2023 | Approved | JESUS RODRIGUEZ |
| Final | 7/21/2023 | Permit Finaled | JESUS RODRIGUEZ |
| HVAC-Final | 7/21/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 7/21/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/21/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 7/21/2023 | Approved | JESUS RODRIGUEZ |