644 N GOWER ST 90004
Certificate Information: 644 N GOWER ST 90004
- Application / Permit
- 21016-10000-43750
- Plan Check / Job No.
- B21LA19758
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING GARAGE AND REC ROOM INTO NEW ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2021 | ADAM HEGAZI |
| Corrections Issued | 10/27/2021 | ADAM HEGAZI |
| Plan Check Approved | 2/28/2022 | ADAM HEGAZI |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Issued | 2/28/2023 | APPLICANT |
| CofO in Progress | 7/27/2024 | JEFFREY MEAD |
| CofO Issued | 8/5/2024 | DEROLD HAUFF |
| Permit Finaled | 8/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 11/19/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2021 | STEVE MELGAR |
| Construction near power lines | Cleared | 2/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 5/22/2023 | Partial Approval | JEFFREY MEAD |
| Pre-Inspection | 5/26/2023 | Approved | JEFFREY MEAD |
| Sewer | 5/26/2023 | Approved | JEFFREY MEAD |
| Underground Mechanical | 5/26/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/30/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 5/30/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 5/30/2023 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 5/30/2023 | Approved | JEFFREY MEAD |
| Underground Mechanical | 5/30/2023 | Approved | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 5/31/2023 | No Access for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 6/2/2023 | Corrections Issued | JEFFREY MEAD |
| Gas Test | 6/2/2023 | No Access for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 6/2/2023 | No Access for Inspection | JEFFREY MEAD |
| HVAC-Rough | 6/5/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Insulation | 6/5/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/5/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 6/13/2023 | Approved | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 6/15/2023 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/5/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/5/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 10/5/2023 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 10/5/2023 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/16/2023 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 10/16/2023 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 10/16/2023 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/25/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 10/25/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/26/2023 | Conditional Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/26/2023 | Approved | JEFFREY MEAD |
| Gas Test | 10/26/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 10/26/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 10/26/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/27/2023 | No Access for Inspection | JEFFREY MEAD |
| Green Building Rough | 10/27/2023 | No Access for Inspection | JEFFREY MEAD |
| Insulation | 10/27/2023 | No Access for Inspection | JEFFREY MEAD |
| Insulation | 12/11/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 12/15/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Not Ready | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/10/2024 | Approved | JEFFREY MEAD |
| Final | 7/10/2024 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 7/10/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 7/10/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 7/10/2024 | Approved | JEFFREY MEAD |
| Final | 7/26/2024 | OK to Issue CofO | JEFFREY MEAD |
| Green Building Final | 7/26/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 7/26/2024 | SGSOV Approved | JEFFREY MEAD |