1157-1159 E 21ST ST 90011

Certificate Information: 1157-1159 E 21ST ST 90011

Application / Permit
21016-10000-43738
Plan Check / Job No.
B21LA19752
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) ATTACHED GARAGE OF A 2 STORY DUPLEX INTO ACCESORY DWELLING UNIT PER GCS 65852.2(e)(1)(c) ***ATTACHED ADU ADDRESS IS 1157 1/2 E 21ST ST***
Permit Issued
Issued on 10/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2021 APPLICANT
Assigned to Plan Check Engineer 10/26/2021 LUKE GONZALES
Corrections Issued 10/27/2021 LUKE GONZALES
Building Plans Picked Up 11/3/2021 APPLICANT
Plan Check Approved 7/19/2022 JOSEPH RAFOLS
Plan Check Approved 8/10/2022 JOSEPH RAFOLS
Issued 10/12/2022 APPLICANT
CofO in Progress 11/19/2024 ALEJANDRO DE ARTOLA
Permit Finaled 11/30/2024 DEROLD HAUFF
CofO Issued 11/30/2024 DEROLD HAUFF
Permit Finaled 11/30/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/7/2022 AMAAN MALIK
Sewer availability Cleared 1/7/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 3/22/2022 AMAAN MALIK
Tenant Habitability Plan Cleared 3/25/2022 MICHAEL SOTO

Contact Information

Contractor Gold Pacific Construction Inc; Lic. No.: 1024672-B 1134 W 68TH ST      LOS ANGELES, CA 90044
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/22/2022 Conditional Approval JULIAN AMAYA
Footing/Foundation/Slab 12/2/2022 Approved JULIAN AMAYA
Pre-Inspection 1/19/2023 Corrections Issued BRENDAN MORELLI
Deputy Drilled-In Anchors 5/22/2023 Conditional Approval BRENDAN MORELLI
Reinforced Concrete Frame 6/2/2023 Approved BRENDAN MORELLI
Wood Frame 6/26/2023 Approved BRENDAN MORELLI
Insulation 7/14/2023 Approved BRENDAN MORELLI
Drywall Nailing 8/15/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/22/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/28/2023 Partial Approval ALEJANDRO DE ARTOLA
Final 3/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 3/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Final 9/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/19/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/19/2024 No Access for Inspection ALEJANDRO DE ARTOLA
Smoke Detectors 9/19/2024 Approved ALEJANDRO DE ARTOLA
Final 10/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Final 11/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 11/15/2024 Approved ALEJANDRO DE ARTOLA
Final 11/18/2024 OK to Issue CofO ALEJANDRO DE ARTOLA