1941 S VICTORIA AVE 90016

Certificate Information: 1941 S VICTORIA AVE 90016

Application / Permit
21016-10000-41250
Plan Check / Job No.
B21LA19452
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING GARAGE INTO ONE (1) ADU AS PER GCS 65852 2(E)(1)(C)
Permit Issued
Issued on 8/31/2022
Issuing Office
Current Status
CofO Issued on 11/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 RICARDO RAMIREZ
Corrections Issued 10/22/2021 RICARDO RAMIREZ
Plan Check Approved 4/14/2022 RICARDO RAMIREZ
Issued 8/31/2022 APPLICANT
Building Plans Picked Up 9/9/2022 APPLICANT
CofO in Progress 12/20/2023 JUSTIN HAWLEY
No Progress 12/20/2023 SCOTT FINNILA
Permit Finaled 11/20/2025 DEROLD HAUFF
CofO Issued 11/20/2025 DEROLD HAUFF
Permit Finaled 11/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/1/2021 JEANIE LAM
Sewer availability Cleared 11/1/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/15/2021 JEANIE LAM
Construction near power lines Cleared 1/25/2022 RIDWAN HARDY
Construction within easement Cleared 3/9/2022 RIDWAN HARDY

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor A R M Builders Inc; Lic. No.: 915352-B 1080 S LA CIENEGA #311      LOS ANGELES, CA 90035
Engineer Grandhi,, Venkata Rohit; Lic. No.: C88709 7157 ALVERN STREET   G319    LOS ANGELES, CA 90045

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/29/2022 Conditional Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 12/7/2022 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 12/7/2022 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 12/8/2022 Approved STUART CHAPMAN
PLUMBING-Rough 12/8/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 2/28/2023 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 2/28/2023 Corrections Issued CALEB MEISTER
HVAC-Rough 2/28/2023 Corrections Issued CALEB MEISTER
PLUMBING-Rough 2/28/2023 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Approved CALEB MEISTER
Insulation 3/22/2023 Not Ready for Inspection CALEB MEISTER
Interior/Exterior Lathing 3/22/2023 Partial Approval CALEB MEISTER
BUILDING-Rough-Frame 4/3/2023 Approved CALEB MEISTER
Drywall Nailing 4/3/2023 Approved CALEB MEISTER
ELECTRICAL-Rough 4/3/2023 Approved CALEB MEISTER
HVAC-Rough 4/3/2023 Approved CALEB MEISTER
Insulation 4/3/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 4/19/2023 Approved MICHAEL LEWIS
Underground Mechanical 6/9/2023 Partial Approval CALEB MEISTER
ELECTRICAL-Final 9/1/2023 Corrections Issued CALEB MEISTER
Final 9/1/2023 Corrections Issued CALEB MEISTER
Green Building Final 9/1/2023 Not Ready for Inspection CALEB MEISTER
HVAC-Final 9/1/2023 Corrections Issued CALEB MEISTER
METHANE-Final 9/1/2023 Approved CALEB MEISTER
PLUMBING-Final 9/1/2023 Corrections Issued CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Approved CALEB MEISTER
Smoke Detectors 9/1/2023 Approved CALEB MEISTER
ELECTRICAL-Final 10/3/2023 Approved CALEB MEISTER
Final 10/3/2023 Corrections Issued CALEB MEISTER
Green Building Final 10/3/2023 Approved CALEB MEISTER
HVAC-Final 10/3/2023 Approved CALEB MEISTER
PLUMBING-Final 10/3/2023 Approved CALEB MEISTER
Final 12/19/2023 OK to Issue CofO JUSTIN HAWLEY
Service/Power Release 12/19/2023 Approved JUSTIN HAWLEY