6702 W 85TH PL 90045

Certificate Information: 6702 W 85TH PL 90045

Application / Permit
21016-10000-38019
Plan Check / Job No.
B21LA19212
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Detached garage conversion to ADU - 327 sf. PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 11/9/2021
Issuing Office
Current Status
Permit Closed on 10/27/2022

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 10/15/2021 ZAW HAN
Corrections Issued 10/18/2021 ZAW HAN
Plan Check Approved 11/3/2021 ZAW HAN
Issued 11/9/2021 APPLICANT
Permit Closed 10/26/2022 BOBBY KEY

Permit Application Clearance Information

CPC Cleared 10/20/2021 LAUREN PADICK
CPC Cleared 10/20/2021 LAUREN PADICK
Address approval Cleared 10/21/2021 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 10/21/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 10/21/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 10/25/2021 HISASHI KOBAYAKAWA
Specific Plan Cleared 10/28/2021 FREDDY GARCIA

Contact Information

Contractor Ccsl Construction Inc; Lic. No.: 1053875-B 208 14TH STREET UNIT B      HUNTINGTON BEACH, CA 92648
Engineer Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 1171 JUSTIN AVE APT 3      GLENDALE, CA 91201

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/10/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 1/10/2022 Not Ready for Inspection BOBBY KEY
Pre-Inspection 1/10/2022 Not Ready for Inspection BOBBY KEY
Excavation/Setback/Form/Re-Bar 1/24/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 1/24/2022 Not Ready for Inspection DAVID FEILER
Pre-Inspection 1/24/2022 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 1/27/2022 Approved BOBBY KEY
Footing/Foundation/Slab 1/27/2022 Approved BOBBY KEY
Excavation/Setback/Form/Re-Bar 2/2/2022 Approved BOBBY KEY
Footing/Foundation/Slab 2/2/2022 Approved BOBBY KEY
ELECTRICAL-Final 10/17/2022 No Access for Inspection BOBBY KEY
HVAC-Final 10/17/2022 No Access for Inspection BOBBY KEY
PLUMBING-Final 10/17/2022 No Access for Inspection BOBBY KEY
Special/Order Compliance 10/26/2022 Permit Closed BOBBY KEY