8119 S KENYON AVE 90045
Certificate Information: 8119 S KENYON AVE 90045
- Application / Permit
- 21016-10000-38014
- Plan Check / Job No.
- B21LA19211
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/8/2022
- Issuing Office
- Current Status
- CofO Issued on 7/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 10/18/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 2/2/2022 | CRYSTEL MAALOUF |
| Issued | 2/8/2022 | APPLICANT |
| CofO in Progress | 7/21/2022 | EVAN COOPER |
| Permit Finaled | 7/28/2022 | DANIEL ORRANTE |
| CofO Issued | 7/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/22/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 10/22/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2021 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 11/9/2021 | PEDRO AYALA |
| Construction near power lines | Cleared | 1/22/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/22/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/7/2022 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 3/24/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 4/28/2022 | Approved | BOBBY KEY |
| Sewer | 4/28/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 5/2/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 5/2/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/4/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 5/4/2022 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Approved | BOBBY KEY |
| Green Building Rough | 5/12/2022 | Approved | BOBBY KEY |
| Insulation | 5/12/2022 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 5/12/2022 | Partial Approval | BOBBY KEY |
| Insulation | 5/13/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 5/17/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/18/2022 | Partial Approval | RICHARD STEINBACH |
| Shower Pan | 5/18/2022 | Approved | RICHARD STEINBACH |
| Final | 6/29/2022 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 6/29/2022 | Approved | BOBBY KEY |
| Final | 7/12/2022 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/12/2022 | SGSOV Not Ready | BOBBY KEY |
| Final | 7/18/2022 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Final | 7/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/19/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Final | 7/21/2022 | OK to Issue CofO | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Approved | EVAN COOPER |