3033-3035 N INGLEDALE TER 90039
Certificate Information: 3033-3035 N INGLEDALE TER 90039
- Application / Permit
- 21016-10000-37071
- Plan Check / Job No.
- B21LA19118
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 530 SQFT TO SINGLE FAMILY DWELLING OF ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c)AND(e)
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2021 | DANIEL SANJUAN |
| Corrections Issued | 10/20/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 1/25/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| Applicant returned to address corrections | 5/27/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 6/21/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 2/9/2023 | LAWRENCE QUIRANTE |
| Plan Check Approved | 2/22/2023 | LUKE GONZALES |
| Issued | 6/14/2023 | APPLICANT |
| CofO in Progress | 7/29/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 7/31/2025 | DEROLD HAUFF |
| CofO Issued | 7/31/2025 | DEROLD HAUFF |
| Permit Finaled | 7/31/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 4/19/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 2/21/2023 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 2/21/2023 | TREVOR QUAN |
Contact Information
| Contractor | Cornerstone Construction And Design; Lic. No.: 775449-B | 4910 MT ROYAL DRIVE LOS ANGELES, CA 90041 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/7/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 7/17/2023 | No Access for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 2/22/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 4/8/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/8/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/8/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/8/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/8/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/15/2024 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 4/15/2024 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/15/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 4/17/2024 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/19/2024 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/30/2024 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 8/16/2024 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 8/16/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 8/16/2024 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Final | 8/20/2024 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 8/20/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 8/20/2024 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 4/10/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 4/14/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Service/Power Release | 4/14/2025 | Partial Approval | NICHOLAS LOPEZ |
| Green Building Final | 6/11/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Final | 6/11/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/11/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 6/13/2025 | Approved | NICHOLAS LOPEZ |
| Final | 6/13/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 6/13/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 6/13/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/13/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Service/Power Release | 6/13/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Smoke Detectors | 6/13/2025 | Approved | NICHOLAS LOPEZ |
| Final | 7/28/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Service/Power Release | 7/28/2025 | Approved | NICHOLAS LOPEZ |