620 S VIRGIL AVE 90005

Certificate Information: 620 S VIRGIL AVE 90005

Application / Permit
21016-10000-37044
Plan Check / Job No.
B21LA19093
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
REMODEL AND REPAIR/REPLACE FINISHES WORK THE SABS FLOOR AND GUEST SERVICE FOR (E) RETAIL STORE/TARGET
Permit Issued
Issued on 1/4/2023
Issuing Office
Current Status
Issued on 1/4/2023

Permit Application Status History

Submitted 12/17/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 SERGIO GUTIERREZ
Green Plans Picked Up 12/30/2021 APPLICANT
Corrections Issued 1/4/2022 SERGIO GUTIERREZ
Quality Review Completed 1/6/2022 FARUK SEZER
Building Plans Picked Up 1/11/2022 APPLICANT
Disabled Access Plans Picked Up 1/11/2022 APPLICANT
Applicant returned to address corrections 8/2/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 9/14/2022 SERGIO GUTIERREZ
Plan Check Approved 12/16/2022 SERGIO GUTIERREZ
Issued 1/4/2023 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 1/14/2022 DALIA MOKAYED
Historic Resource Verification Cleared 3/2/2022 MAX LODER
Redevelopment Project Area Cleared 3/21/2022 DAVID URITA
DAS Clearance Cleared 8/16/2022 SHINE LIN
Green Code Cleared 8/16/2022 AARON COSTA

Contact Information

Architect Sargenti,, Robert Jon; Lic. No.: C31054 461 FROM ROAD SUITE 255      PARAMUS, NJ 07652
Contractor Groom Construction Co Inc; Lic. No.: 936386-B 96 SWAMPSCOTT ROAD      SALEM, MA 01970
Engineer Kramer,, James Richard; Lic. No.: S5165 21752 ESMALTE#4      MISSION VIEJO, CA 92692

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 1/20/2023 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 1/20/2023 Not Ready for Inspection RONALD JIMENEZ
Light Gage Steel Frame 2/2/2023 Partial Approval MARTIN TAVITIAN
Drywall Nailing 2/7/2023 Partial Approval JULIAN CAPUCETTI
Light Gage Steel Frame 2/21/2023 Approved ALAN MORELOS
Drywall Nailing 2/23/2023 Approved JAIME RIOS
Final 3/30/2023 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 3/30/2023 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 3/30/2023 Not Ready for Inspection ALFREDO LOPEZ
Final 9/13/2023 Not Ready for Inspection TIMOTHY POWELL
Green Building Final 9/13/2023 Not Ready for Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 9/13/2023 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 9/13/2023 Not Ready for Inspection TIMOTHY POWELL
Final 10/11/2023 Corrections Issued RAFAEL CORTES
Green Building Final 10/11/2023 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 10/11/2023 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 10/11/2023 Approved RAFAEL CORTES
Final 10/19/2023 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 10/19/2023 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 10/19/2023 SGSOV Not Ready ALFREDO LOPEZ