8201 N WOODLEY AVE 91406
Certificate Information: 8201 N WOODLEY AVE 91406
- Application / Permit
- 21016-10000-37043
- Plan Check / Job No.
- B21LA19092
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- TENANT IMPROVEMENT - TWO NEW DOORS THROUGH CONCRETE WALLS AT EXISTING WAREHOUSE AREA. EXISTING OCCUPANTS TO REMAIN
- Permit Issued
- Issued on 5/17/2022
- Issuing Office
- Current Status
- Permit Finaled on 12/9/2022
Permit Application Status History
| Submitted | 10/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 10/21/2021 | RACHEL BEYENE |
| Applicant returned to address corrections | 11/6/2021 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Plan Check Approved | 5/16/2022 | ARTIN ZARUKIAN |
| Issued | 5/17/2022 | APPLICANT |
| Permit Finaled | 12/8/2022 | DEANDRE HOFFMAN |
Permit Application Clearance Information
| ZA Case | Cleared | 12/20/2021 | PABLO ESTRADA |
Contact Information
| Architect | Fridlund,, David John; Lic. No.: C20787 | 1917 SILVER WOOD LANE LOS ANGELES, CA 90041 |
| Contractor | Corporate Contractors Inc; Lic. No.: 604407-B | 2550 CORPORATE PL STE C-111 MONTEREY PARK, CA 91754 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 7/21/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 7/22/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 7/25/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 7/26/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 7/26/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 7/27/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 7/27/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 8/23/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 8/23/2022 | Conditional Approval | JEFFREY FULTON |
| Light Gage Steel Frame | 9/22/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Structural Steel Frame | 9/22/2022 | Partial Inspection | JEFFREY FULTON |
| Final | 12/8/2022 | Permit Finaled | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 12/8/2022 | Approved | DEANDRE HOFFMAN |