4603 W FINLEY AVE 90027

Certificate Information: 4603 W FINLEY AVE 90027

Application / Permit
21016-10000-36506
Plan Check / Job No.
B21LA18970
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: By adding a SSCC at south elevation
Permit Issued
Issued on 8/3/2022
Issuing Office
Current Status
CofC Issued on 12/16/2022

Permit Application Status History

Submitted 10/7/2021 APPLICANT
Assigned to Plan Check Engineer 11/10/2021 JESSE VIDUYA
Corrections Issued 11/18/2021 JESSE VIDUYA
Quality Review Completed 11/24/2021 SAI KHUM
Applicant returned to address corrections 3/8/2022 JESSE VIDUYA
Plan Check Approved 4/19/2022 JESSE VIDUYA
Issued 8/3/2022 APPLICANT
OK for CofC 12/16/2022 VAHE KELEDJIAN
CofC Issued 12/16/2022 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 8/2/2022 RICARDO BOHORQUEZ

Contact Information

Contractor Sks Construction; Lic. No.: 720390-B 15134 FRIAR STREET      VAN NUYS, CA 91411
Engineer Shaolian,, Shahab Joseph; Lic. No.: C84155 5104 GARDEN GROVE      TARZANA, CA 91356

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/22/2022 Approved BRUCE CAMPBELL
Deputy Drilled-In Anchors 9/1/2022 Conditional Approval BRUCE CAMPBELL
Deputy Drilled-In Anchors 9/6/2022 Conditional Approval BRUCE CAMPBELL
Deputy Reinf. Concrete 9/7/2022 Conditional Approval BRUCE CAMPBELL
Footing/Foundation/Slab 9/7/2022 Corrections Issued BRUCE CAMPBELL
Structural Steel Frame 9/7/2022 Partial Approval BRUCE CAMPBELL
Deputy Reinf. Concrete 9/30/2022 No Access for Inspection BRUCE CAMPBELL
Deputy Reinf. Concrete 10/3/2022 Conditional Approval BRUCE CAMPBELL
Footing/Foundation/Slab 10/3/2022 Approved BRUCE CAMPBELL
Wood Frame 10/3/2022 Not Ready for Inspection BRUCE CAMPBELL
Reinforced Concrete Frame 10/7/2022 Approved DANIEL VARNUM
Wood Frame 10/13/2022 Approved DANIEL VARNUM
Interior/Exterior Lathing 10/24/2022 Partial Approval DARRYL ARNOLD
Final 12/9/2022 Corrections Issued VAHE KELEDJIAN
SGSOV-Seismic Gas S/O Valve 12/9/2022 SGSOV Approved VAHE KELEDJIAN
Smoke Detectors 12/9/2022 Approved VAHE KELEDJIAN
Final 12/16/2022 OK for CofC VAHE KELEDJIAN