726 1/2 N MILO TER 90042

Certificate Information: 726 1/2 N MILO TER 90042

Application / Permit
21016-10000-36316
Plan Check / Job No.
B21LA18870
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT
Permit Issued
Issued on 3/16/2022
Issuing Office
Current Status
CofO Issued on 1/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2021 APPLICANT
Assigned to Plan Check Engineer 10/15/2021 FERNANDO FLORES
Corrections Issued 10/19/2021 FERNANDO FLORES
Plan Check Approved 11/24/2021 FERNANDO FLORES
Issued 3/16/2022 APPLICANT
Building Plans Picked Up 3/17/2022 APPLICANT
CofO in Progress 1/24/2023 HAMIK HARTOUNIAN
CofO Issued 1/27/2023 DEROLD HAUFF
Permit Finaled 1/27/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/1/2021 PATRICK MISCHLICH
Address approval Cleared 11/3/2021 ABEL CASILLAS
Sewer availability Cleared 11/3/2021 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 11/10/2021 ABEL CASILLAS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 3/23/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 3/23/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Sewer 3/23/2022 Approved HAMIK HARTOUNIAN
Underground Mechanical 3/23/2022 Conditional Approval HAMIK HARTOUNIAN
Pre-Inspection 4/6/2022 Approved HAMIK HARTOUNIAN
Pre-Inspection 5/9/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/25/2022 Approved HAMIK HARTOUNIAN
Pre-Inspection 9/8/2022 Partial Inspection HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 9/22/2022 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/11/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 10/11/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 10/11/2022 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/31/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/31/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 10/31/2022 Approved HAMIK HARTOUNIAN
Insulation 10/31/2022 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 10/31/2022 Approved HAMIK HARTOUNIAN
Insulation 11/15/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/15/2022 Partial Approval HAMIK HARTOUNIAN
Shower Pan 11/15/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 11/21/2022 Approved AMY COLIN
Interior/Exterior Lathing 12/6/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 1/11/2023 Approved HAMIK HARTOUNIAN
Final 1/11/2023 Corrections Issued HAMIK HARTOUNIAN
Gas Test 1/11/2023 Approved HAMIK HARTOUNIAN
Green Building Final 1/11/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 1/11/2023 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 1/11/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/11/2023 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 1/11/2023 Not Required HAMIK HARTOUNIAN
Smoke Detectors 1/11/2023 Approved HAMIK HARTOUNIAN
Final 1/19/2023 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 1/19/2023 Approved HAMIK HARTOUNIAN