2213 W SUNSET BLVD 90026
Certificate Information: 2213 W SUNSET BLVD 90026
- Application / Permit
- 21016-10000-36297
- Plan Check / Job No.
- B21LA18849
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Take Out
- Work Description
- Change of use from Retail to Take-Out Restaurant (No seating) hours of operation from 7am to 11pm.
- Permit Issued
- Issued on 2/24/2022
- Issuing Office
- Current Status
- CofO Issued on 12/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Application Withdrawn-Void | 10/8/2021 | TAMERA SVETICH |
| Re-Activate Application | 10/8/2021 | FELIX FIGUEROA |
| Submitted | 10/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2021 | SALVADOR QUINTANILLA |
| Plan Check Approved | 2/14/2022 | SALVADOR QUINTANILLA |
| Issued | 2/24/2022 | APPLICANT |
| Building Plans Picked Up | 2/25/2022 | APPLICANT |
| CofO in Progress | 12/2/2022 | EDWIN GREGORYONA |
| CofO in Progress | 12/2/2022 | EDWIN GREGORYONA |
| CofO Issued | 12/8/2022 | TED RIES |
| Permit Finaled | 12/8/2022 | TED RIES |
Permit Application Clearance Information
| "Q" conditions | Cleared | 11/10/2021 | MAXFIELD VERMY |
| Comm Cor/Mini-Mall | Cleared | 11/10/2021 | MAXFIELD VERMY |
| ZA Case | Cleared | 11/10/2021 | MAXFIELD VERMY |
| ZA Case | Cleared | 11/10/2021 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 1/24/2022 | ABEL CASILLAS |
| Food establishment approval | Cleared | 2/10/2022 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 2/11/2022 | PAWAN VERMA |
Contact Information
| Contractor | Handyman Construction Services Inc; Lic. No.: 986371-B | 1847 CALAFIA STREET GLENDALE, CA 91208 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 5/25/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Drywall Nailing | 6/10/2022 | Partial Approval | JONATHAN QUACH |
| Wood Frame | 6/10/2022 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 6/13/2022 | Approved | RAFAEL ESPINOZA |
| Final | 9/22/2022 | Not Ready for Inspection | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Not Ready | GREGORY POMISH |
| Smoke Detectors | 9/22/2022 | Not Ready for Inspection | GREGORY POMISH |
| Final | 11/18/2022 | OK to Issue CofO | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 11/18/2022 | Approved | EDWIN GREGORYONA |