6363 W SELMA AVE 90028

Certificate Information: 6363 W SELMA AVE 90028

Application / Permit
21016-10000-36286
Plan Check / Job No.
B21LA18832
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Museum for profit
Work Description
CHANGE OF USE FROM RECORDING STUDIO TO RETAIL/ MUSEUM. MAXIMUM OCCUPANT LOAD FOR THE ENTIRE BUILDING IS 98. INSTALL NEW ELEVATOR AND STAIRWAY. INSTALL NEW STORE-FRONT GLASS ENTRYWAY, INSTALL NEW STRUCTURAL BEAMS TO REPLACE (E) PARTITION WALLS.
Permit Issued
Issued on 2/10/2022
Issuing Office
Current Status
CofO Issued on 4/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 LARRY LEE
Corrections Issued 10/27/2021 LARRY LEE
Quality Review Completed 10/28/2021 SAI KHUM
Building Plans Picked Up 11/1/2021 APPLICANT
Applicant returned to address corrections 12/22/2021 LARRY LEE
Plan Check Approved 2/4/2022 LARRY LEE
Issued 2/10/2022 APPLICANT
CofO in Progress 4/26/2023 ERNESTO CORRAL
CofO Issued 4/26/2023 ERNESTO CORRAL
Permit Finaled 4/26/2023 ERNESTO CORRAL

Permit Application Clearance Information

ZI Cleared 11/5/2021 MAXFIELD VERMY
City Hist. Cultural Monument Cleared 11/9/2021 MICAELA TORRES-GIL
Historic Resource Verification Cleared 11/9/2021 MICAELA TORRES-GIL
Historic monument Cleared 11/9/2021 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 11/10/2021 DAVID URITA
Eng Process Fee Ord 176,300 Cleared 11/15/2021 ABEL CASILLAS
Sewer availability Cleared 11/15/2021 ABEL CASILLAS
Fire Marshal Fire Life Safety Cleared 12/17/2021 VIDAL GARCIA
DAS Clearance Cleared 1/25/2022 SHINE LIN

Contact Information

Contractor Hahn Contractors Inc; Lic. No.: 807850-B 21040 PLACERITA CYN RD      NEWHALL, CA 91321

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/25/2022 Not Ready for Inspection JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 3/4/2022 Partial Approval JONATHAN QUACH
Deputy Steel/Welding 3/15/2022 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 3/16/2022 Conditional Approval JONATHAN QUACH
Wood Frame 3/31/2022 Corrections Issued SORIN CIRSTOIU
Deputy Reinf. Concrete 4/26/2022 Conditional Approval JONATHAN QUACH
Structural Steel Frame 5/11/2022 Partial Inspection SORIN CIRSTOIU
Wall Anchors 5/11/2022 Partial Inspection SORIN CIRSTOIU
Wood Frame 5/11/2022 Partial Inspection SORIN CIRSTOIU
Structural Steel Frame 6/8/2022 Approved RAFAEL ESPINOZA
Wood Frame 6/8/2022 Approved RAFAEL ESPINOZA
Drywall Nailing 6/22/2022 Partial Approval JONATHAN QUACH
Drywall Nailing 6/28/2022 Approved GREGORY POMISH
Final 1/4/2023 Corrections Issued KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 1/4/2023 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 1/4/2023 Approved KATY RAMIREZ
Final 1/20/2023 Partial Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Approved RONALD JIMENEZ
Special/Order Compliance 1/23/2023 Corrections Issued RONALD JIMENEZ
Final 4/21/2023 Conditional Approval RONALD JIMENEZ