1137-1139 E LAKE ST 90291
Certificate Information: 1137-1139 E LAKE ST 90291
- Application / Permit
- 21016-10000-36273
- Plan Check / Job No.
- B21LA18822
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Converted Existing attached 2 car garage into ADU -336sq.ft.
- Permit Issued
- Issued on 11/29/2021
- Issuing Office
- Current Status
- Issued on 11/29/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2021 | HERNAN ARREOLA |
| Corrections Issued | 10/11/2021 | HERNAN ARREOLA |
| Plan Check Approved | 11/11/2021 | HERNAN ARREOLA |
| Issued | 11/29/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/28/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 10/28/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 3/18/2022 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 3/18/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 3/22/2022 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 3/22/2022 | Partial Approval | DAVID FEILER |
| Interior/Exterior Lathing | 3/25/2022 | Partial Approval | KRISTEN CAUSEY |
| Wood Frame | 3/30/2022 | Corrections Issued | KENNETH NAGLE |
| Green Building Rough | 4/1/2022 | Approved | ANDREW NAVE |
| Wood Frame | 4/1/2022 | Approved | ANDREW NAVE |
| Insulation | 4/5/2022 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/5/2022 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 4/11/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 4/11/2022 | Not Ready for Inspection | DAVID FEILER |
| Wall Anchors | 4/13/2022 | Not Ready for Inspection | DAVID FEILER |
| Drywall Nailing | 4/18/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 4/18/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 5/5/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Special/Order Compliance | 10/3/2022 | Partial Inspection | CLAYTON GRAHAM |
| Drywall Nailing | 12/12/2022 | Approved | EVAN COOPER |
| Final | 12/12/2022 | Corrections Issued | EVAN COOPER |
| Green Building Final | 12/12/2022 | Not Ready for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/12/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 12/12/2022 | Approved | EVAN COOPER |
| Wood Frame | 12/12/2022 | Approved | EVAN COOPER |