833 W 165TH PL 90247

Certificate Information: 833 W 165TH PL 90247

Application / Permit
21016-10000-36201
Plan Check / Job No.
B21LA18806
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT EXISTING ATTACHED GARAGE INTO ONE ACCESSORY DWELLING UNIT
Permit Issued
Issued on 7/28/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2021 APPLICANT
Assigned to Plan Check Engineer 10/15/2021 FERNANDO FLORES
Corrections Issued 10/19/2021 FERNANDO FLORES
Applicant returned to address corrections 1/18/2022 GEORGE ALVAREZ
Building Plans Picked Up 1/24/2022 APPLICANT
Plan Check Approved 4/13/2022 SHANGQIN XIE
Issued 7/28/2022 APPLICANT
CofO in Progress 11/30/2023 JOEY BUCHANAN
Permit Finaled 12/15/2023 DAVID TSAU
CofO Issued 12/15/2023 DAVID TSAU
Permit Finaled 12/15/2023 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 12/8/2021 WALLIE JONG
Sewer availability Cleared 12/8/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/13/2021 WALLIE JONG
Tenant Habitability Plan Cleared 12/15/2021 ISMAEL HERNANDEZ

Contact Information

Architect Gubel,, Gustavo A; Lic. No.: C26190 5455 WILSHIRE BLVD #1013      LOS ANGELES, CA 90036
Contractor J N Builds Inc; Lic. No.: 1055529-B 1514 CURTIS AVE      MANHATTAN BEACH, CA 90266
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 2919 BURBANK BLVD STE D      BURBANK, CA 91505

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/11/2022 Approved DAVID TSAU
Green Building Rough 10/7/2022 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 10/7/2022 Corrections Issued JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 1/17/2023 Not Ready for Inspection AMANUEL BERHE
Green Building Rough 1/17/2023 Not Ready for Inspection AMANUEL BERHE
Wood Frame 1/17/2023 Not Ready for Inspection AMANUEL BERHE
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Not Ready for Inspection JOEY BUCHANAN
Green Building Rough 1/20/2023 Approved JOEY BUCHANAN
Insulation 1/20/2023 Approved JOEY BUCHANAN
Wood Frame 1/20/2023 Approved JOEY BUCHANAN
Drywall Nailing 1/30/2023 Approved JOEY BUCHANAN
Final 10/11/2023 Not Ready for Inspection AMANUEL BERHE
Green Building Final 10/11/2023 Not Ready for Inspection AMANUEL BERHE
SGSOV-Seismic Gas S/O Valve 10/11/2023 SGSOV Not Ready AMANUEL BERHE
Smoke Detectors 10/11/2023 Not Ready for Inspection AMANUEL BERHE
Final 11/9/2023 Not Ready for Inspection DARRYL ARNOLD
Green Building Final 11/9/2023 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 11/9/2023 Conditional Approval DARRYL ARNOLD
Final 11/16/2023 Not Ready for Inspection AMANUEL BERHE
Green Building Final 11/16/2023 Not Ready for Inspection AMANUEL BERHE
SGSOV-Seismic Gas S/O Valve 11/16/2023 SGSOV Approved AMANUEL BERHE
Smoke Detectors 11/16/2023 Not Ready for Inspection AMANUEL BERHE
Green Building Final 11/22/2023 Approved JOEY BUCHANAN
Smoke Detectors 11/22/2023 Approved JOEY BUCHANAN
Final 11/29/2023 OK to Issue CofO JOEY BUCHANAN