833 W 165TH PL 90247
Certificate Information: 833 W 165TH PL 90247
- Application / Permit
- 21016-10000-36201
- Plan Check / Job No.
- B21LA18806
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT EXISTING ATTACHED GARAGE INTO ONE ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2021 | FERNANDO FLORES |
| Corrections Issued | 10/19/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 1/18/2022 | GEORGE ALVAREZ |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| Plan Check Approved | 4/13/2022 | SHANGQIN XIE |
| Issued | 7/28/2022 | APPLICANT |
| CofO in Progress | 11/30/2023 | JOEY BUCHANAN |
| Permit Finaled | 12/15/2023 | DAVID TSAU |
| CofO Issued | 12/15/2023 | DAVID TSAU |
| Permit Finaled | 12/15/2023 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 12/8/2021 | WALLIE JONG |
| Sewer availability | Cleared | 12/8/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2021 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 12/15/2021 | ISMAEL HERNANDEZ |
Contact Information
| Architect | Gubel,, Gustavo A; Lic. No.: C26190 | 5455 WILSHIRE BLVD #1013 LOS ANGELES, CA 90036 |
| Contractor | J N Builds Inc; Lic. No.: 1055529-B | 1514 CURTIS AVE MANHATTAN BEACH, CA 90266 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 2919 BURBANK BLVD STE D BURBANK, CA 91505 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/11/2022 | Approved | DAVID TSAU |
| Green Building Rough | 10/7/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 10/7/2022 | Corrections Issued | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Green Building Rough | 1/17/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Wood Frame | 1/17/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Not Ready for Inspection | JOEY BUCHANAN |
| Green Building Rough | 1/20/2023 | Approved | JOEY BUCHANAN |
| Insulation | 1/20/2023 | Approved | JOEY BUCHANAN |
| Wood Frame | 1/20/2023 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 1/30/2023 | Approved | JOEY BUCHANAN |
| Final | 10/11/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Green Building Final | 10/11/2023 | Not Ready for Inspection | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Not Ready | AMANUEL BERHE |
| Smoke Detectors | 10/11/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Final | 11/9/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Green Building Final | 11/9/2023 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 11/9/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 11/16/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Green Building Final | 11/16/2023 | Not Ready for Inspection | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Approved | AMANUEL BERHE |
| Smoke Detectors | 11/16/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Green Building Final | 11/22/2023 | Approved | JOEY BUCHANAN |
| Smoke Detectors | 11/22/2023 | Approved | JOEY BUCHANAN |
| Final | 11/29/2023 | OK to Issue CofO | JOEY BUCHANAN |