2837-2841 S CRENSHAW BLVD 90016
Certificate Information: 2837-2841 S CRENSHAW BLVD 90016
- Application / Permit
- 21016-10000-34714
- Plan Check / Job No.
- B21LA18695
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Shopping Center
- Work Description
- DIVISION OF EXISTING RETAIL SPACE TO CREATE THREE (3) RETAILS SPACES. (NO TENANT IMPROVEMENT)
- Permit Issued
- Issued on 2/17/2023
- Issuing Office
- Metro
- Current Status
- Issued on 2/17/2023
Permit Application Status History
| Submitted | 10/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | RACHEL BEYENE |
| Corrections Issued | 10/8/2021 | RACHEL BEYENE |
| Building Plans Picked Up | 11/17/2021 | APPLICANT |
| Applicant returned to address corrections | 4/15/2022 | RACHEL BEYENE |
| Applicant returned to address corrections | 8/2/2022 | ADAM HEGAZI |
| Plan Check Approved | 8/11/2022 | SHANGQIN XIE |
| Issued | 2/17/2023 | APPLICANT |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 12/14/2021 | GRACIELA ACOSTA |
| Specific Plan | Cleared | 5/23/2022 | KYLE WINSTON |
| ZA Case | Cleared | 6/30/2022 | DALIA MOKAYED |
Contact Information
| Contractor | Sun Construction; Lic. No.: 1012171-B | 7700 LAMPSOM AVENUE #115 GARDEN GROVE, CA 92841 |
| Engineer | Tagudar,, Fred; Lic. No.: C33612 | 255 W 5TH ST APT 706 SAN PEDRO, CA 90731 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 3/21/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 4/25/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/25/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/25/2023 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/4/2023 | SGSOV Not Ready | ALFREDO LOPEZ |
| Final | 5/9/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Not Ready | ALFREDO LOPEZ |
| Final | 6/14/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Not Ready | ALFREDO LOPEZ |
| Final | 5/21/2024 | Corrections Issued | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Not Ready | DARRYL ARNOLD |