877 S FRANCISCO ST 277 90017
Certificate Information: 877 S FRANCISCO ST 277 90017
- Application / Permit
- 21016-10000-34188
- Plan Check / Job No.
- B21LA18596
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Beauty Shop or Parlor
- Work Description
- eplan: PROJECT IS A TENANT FINISH-OUT OF AN EXISTING SPACE IN A SHELL RETAIL BUILDING CONSISTING OF INDIVIDUAL SALON SUITES, RESTROOMS, AND A STORAGE / UTILITY ROOM, AND COMMON BREAK AREA. NO EXTERIOR MODIFICATIONS TO SHELL BUILDING DESIGN. EXISTING STOREFRONT TO REMAIN, REPLACE ONE STOREFRONT DOOR WITH GLAZING PANEL.
- Permit Issued
- Issued on 8/30/2022
- Issuing Office
- Current Status
- Issued on 8/30/2022
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 10/26/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/11/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/15/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 3/8/2022 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 3/15/2022 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 7/1/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 7/6/2022 | ARSALAN SHABESTARI |
| Issued | 8/30/2022 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 4/13/2022 | NORLITO MEDRANO |
| Green Code | Cleared | 5/2/2022 | AARON COSTA |
Contact Information
| Architect | Gerdes,, F Andrew; Lic. No.: NA17261 | , |
| Contractor | Limestone General Contractor; Lic. No.: 1023749-B | , |
| Engineer | Roberts,, Ronald Andrew; Lic. No.: NA41650 | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/5/2022 | Partial Inspection | KATY RAMIREZ |
| Drywall Nailing | 12/8/2022 | Partial Approval | KATY RAMIREZ |
| Insulation | 1/9/2023 | Corrections Issued | TIMOTHY POWELL |
| Drywall Nailing | 1/24/2023 | Approved | KATY RAMIREZ |
| T-Bar Ceiling | 5/22/2023 | Corrections Issued | KATY RAMIREZ |
| T-Bar Ceiling | 5/24/2023 | Partial Inspection | KATY RAMIREZ |
| T-Bar Ceiling | 6/8/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 8/2/2023 | Partial Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 8/2/2023 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 8/2/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Smoke Detectors | 8/7/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 8/9/2023 | Partial Inspection | KATY RAMIREZ |
| Smoke Detectors | 8/9/2023 | Partial Inspection | KATY RAMIREZ |