813 N GENESEE AVE 90046
Certificate Information: 813 N GENESEE AVE 90046
- Application / Permit
- 21016-10000-34152
- Plan Check / Job No.
- B21LA18582
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | DANIEL YIP |
| Corrections Issued | 10/26/2021 | DANIEL YIP |
| Quality Review Completed | 11/5/2021 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 12/15/2021 | DANIEL YIP |
| Plan Check Approved | 2/22/2022 | DANIEL YIP |
| Issued | 3/3/2022 | APPLICANT |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| CofO in Progress | 2/17/2026 | JOSH MEISTER |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| CofO Issued | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2021 | CELINA MORENO |
| Sewer availability | Cleared | 11/19/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2021 | CELINA MORENO |
| Construction near power lines | Cleared | 2/11/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/16/2024 | Partial Approval | AMIR NAZARIAN |
| Footing/Foundation/Slab | 6/5/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 6/11/2024 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/13/2024 | Partial Approval | AMIR NAZARIAN |
| Pre-Inspection | 8/13/2024 | Partial Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/23/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 8/29/2024 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Approved | JOSE MACIAS |
| Shower Pan | 10/16/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 10/29/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 10/31/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 10/31/2024 | Approved | JOSE MACIAS |
| Deputy Wood Construction | 11/13/2024 | Conditional Approval | JOSE MACIAS |
| Interior/Exterior Lathing | 11/21/2024 | Approved | JOSE MACIAS |
| Insulation | 12/5/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 12/6/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 12/6/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 1/24/2025 | Approved | JOSE MACIAS |
| Sewer | 4/17/2025 | Approved | WAYNE REGESTER |
| Underground Mechanical | 4/28/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 8/26/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/7/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 11/7/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 1/28/2026 | Corrections Issued | JOSH MEISTER |
| Green Building Final | 1/28/2026 | Not Ready for Inspection | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Not Ready | JOSH MEISTER |
| Smoke Detectors | 1/28/2026 | Corrections Issued | JOSH MEISTER |
| Final | 2/4/2026 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Final | 2/4/2026 | Not Ready for Inspection | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 2/4/2026 | SGSOV Not Ready | JOSH MEISTER |
| Smoke Detectors | 2/4/2026 | Not Ready for Inspection | JOSH MEISTER |
| Final | 2/6/2026 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Final | 2/6/2026 | Not Ready for Inspection | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 2/6/2026 | SGSOV Not Ready | JOSH MEISTER |
| Smoke Detectors | 2/6/2026 | Not Ready for Inspection | JOSH MEISTER |
| Final | 2/11/2026 | OK to Issue CofO | JOSH MEISTER |
| Green Building Final | 2/11/2026 | Approved | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 2/11/2026 | SGSOV Approved | JOSH MEISTER |
| Smoke Detectors | 2/11/2026 | Approved | JOSH MEISTER |