4822-4824 N LA RODA AVE 90041

Certificate Information: 4822-4824 N LA RODA AVE 90041

Application / Permit
21016-10000-33094
Plan Check / Job No.
B21LA18561
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan CONVERT EXISTING ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
CofO Issued on 9/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2021 APPLICANT
Assigned to Plan Check Engineer 10/20/2021 MICHAEL LOPEZ
Corrections Issued 10/20/2021 MICHAEL LOPEZ
Applicant returned to address corrections 12/14/2021 MICHAEL LOPEZ
Applicant returned to address corrections 12/16/2021 MICHAEL LOPEZ
Plan Check Approved 1/7/2022 MICHAEL LOPEZ
Issued 2/14/2022 APPLICANT
CofO in Progress 9/1/2022 CRAIG VAUGHAN
CofO in Progress 9/1/2022 CRAIG VAUGHAN
Permit Finaled 9/8/2022 DEROLD HAUFF
CofO Issued 9/8/2022 DEROLD HAUFF
Permit Finaled 9/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/28/2021 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 10/28/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 12/21/2021 CINDY QI
Sewer availability Cleared 12/21/2021 CINDY QI
Grading Pre-Inspection Cleared 1/3/2022 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C93320       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/16/2022 Partial Approval CRAIG VAUGHAN
Sewer 3/31/2022 Approved SCOTT FINNILA
Underground Mechanical 3/31/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 5/10/2022 Corrections Issued CRAIG VAUGHAN
Sewer 5/10/2022 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 5/12/2022 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 5/23/2022 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 6/9/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/22/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 6/22/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 6/22/2022 Approved CRAIG VAUGHAN
HVAC-Rough 6/22/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 7/12/2022 Approved CRAIG VAUGHAN
HVAC-Rough 7/12/2022 Approved CRAIG VAUGHAN
Insulation 7/12/2022 Approved CRAIG VAUGHAN
Wood Frame 7/12/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/18/2022 Partial Approval CRAIG VAUGHAN
Drywall Nailing 7/21/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/21/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/27/2022 Approved CRAIG VAUGHAN
Shower Pan 7/27/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 8/19/2022 Approved CRAIG VAUGHAN
Final 8/25/2022 Corrections Issued CRAIG VAUGHAN
Green Building Final 8/25/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/25/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 8/25/2022 Approved CRAIG VAUGHAN
Final 8/31/2022 OK to Issue CofO CRAIG VAUGHAN