3798 S GRAMERCY PL 90062

Certificate Information: 3798 S GRAMERCY PL 90062

Application / Permit
21016-10000-33090
Plan Check / Job No.
B21LA18560
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) 2 car detached garage into an ADU.
Permit Issued
Issued on 12/14/2021
Issuing Office
Current Status
CofO Issued on 1/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2021 APPLICANT
Assigned to Plan Check Engineer 10/6/2021 JOE VO
Corrections Issued 10/6/2021 JOE VO
Plan Check Approved 11/21/2021 JOE VO
Issued 12/14/2021 APPLICANT
CofO in Progress 1/6/2023 SABAS ALONSO
Permit Finaled 1/11/2023 DEROLD HAUFF
CofO Issued 1/11/2023 DEROLD HAUFF
Permit Finaled 1/11/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/12/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 10/12/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 10/12/2021 CHRISTOPHER ROCHA

Contact Information

Contractor Choe Craig; Lic. No.: 867838-B 3183 WILSHIRE BLVD   196 - E33    LOS ANGELES, CA 90010

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

HVAC-Rough 4/1/2022 Corrections Issued SABAS ALONSO
PLUMBING-Rough 4/1/2022 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 4/1/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 4/25/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 4/28/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 5/2/2022 Partial Approval SABAS ALONSO
HVAC-Rough 5/2/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 5/11/2022 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/28/2022 Approved SABAS ALONSO
ELECTRICAL-Final 6/28/2022 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 6/28/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Partial Approval SABAS ALONSO
Green Building Rough 6/28/2022 Approved SABAS ALONSO
HVAC-Rough 6/28/2022 Approved SABAS ALONSO
PLUMBING-Rough 6/28/2022 Approved SABAS ALONSO
Insulation 7/11/2022 No Access for Inspection HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 7/19/2022 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 7/19/2022 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 7/25/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 7/25/2022 Partial Approval HORACE FULTZ
Interior/Exterior Lathing 8/5/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/25/2022 SGSOV Not Ready JOAQUIN GREENOUGH
HVAC-Final 9/29/2022 Corrections Issued SABAS ALONSO
PLUMBING-Final 9/29/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 10/17/2022 Approved SABAS ALONSO
HVAC-Final 10/17/2022 Approved SABAS ALONSO
PLUMBING-Final 10/17/2022 Approved SABAS ALONSO
Final 11/8/2022 Corrections Issued SABAS ALONSO
Green Building Final 11/8/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved SABAS ALONSO
Smoke Detectors 11/8/2022 Approved SABAS ALONSO
Final 1/6/2023 OK to Issue CofO SABAS ALONSO