2104-2106 S CRENSHAW BLVD 90016

Certificate Information: 2104-2106 S CRENSHAW BLVD 90016

Application / Permit
21016-10000-32860
Plan Check / Job No.
B21LA18523
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
INTERIOR/EXTERIOR REMODEL TO (E) TWO-STORY SINGLE FAMILY DWELLING. SCOPE OF WORK TO INCLUDE CONVERTING (E) SFD TO DUPLEX. ALL WORK PER ENGINEERED DESIGN. (COMPLY WITH DEPARTMENT ORDER effective date 09/14/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE)
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 9/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2021 APPLICANT
Assigned to Plan Check Engineer 11/9/2021 FARSHAD ALIMOHAMADI
Corrections Issued 11/17/2021 FARSHAD ALIMOHAMADI
Quality Review Completed 11/18/2021 SAI KHUM
Applicant returned to address corrections 12/22/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 2/18/2022 FARSHAD ALIMOHAMADI
Issued 3/2/2022 APPLICANT
Building Plans Picked Up 3/4/2022 APPLICANT
CofO in Progress 9/13/2022 WILLIAM MICHALAK
Permit Finaled 9/19/2022 BRUCE TODD
CofO Issued 9/19/2022 BRUCE TODD
Permit Finaled 9/19/2022 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 12/3/2021 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 12/6/2021 KHOUNG LE
Sewer availability Cleared 12/6/2021 KHOUNG LE

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/27/2022 Corrections Issued WILLIAM MICHALAK
BUILDING-Rough-Frame 5/24/2022 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Rough 5/24/2022 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 5/27/2022 Partial Approval WILLIAM MICHALAK
PLUMBING-Rough 5/27/2022 Approved WILLIAM MICHALAK
Insulation 6/1/2022 Approved WILLIAM MICHALAK
PLUMBING-Rough 6/1/2022 Approved WILLIAM MICHALAK
Drywall Nailing 6/8/2022 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 8/9/2022 Corrections Issued WILLIAM MICHALAK
Final 8/9/2022 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 8/9/2022 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 8/22/2022 Corrections Issued WILLIAM MICHALAK
Final 8/22/2022 Corrections Issued WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Not Ready WILLIAM MICHALAK
BUILDING-Rough-Frame 8/23/2022 Approved WILLIAM MICHALAK
Final 8/23/2022 Corrections Issued WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 8/23/2022 SGSOV Approved WILLIAM MICHALAK
Final 9/13/2022 OK to Issue CofO WILLIAM MICHALAK