629 1/2-3/4 W 56TH ST 90037

Certificate Information: 629 1/2-3/4 W 56TH ST 90037

Application / Permit
21016-10000-32479
Plan Check / Job No.
B21LA18389
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 1ST FLOOR GARAGE 507 SF INTO AN ADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 9/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 DANIEL SANJUAN
Corrections Issued 11/24/2021 DANIEL SANJUAN
Applicant returned to address corrections 1/22/2022 TSE MING HUANG
Applicant returned to address corrections 3/1/2022 STANLEY RAAP
Building Plans Picked Up 5/12/2022 APPLICANT
Plan Check Approved 5/17/2022 RAHEL BEYENE
Issued 9/5/2023 APPLICANT
CofO in Progress 6/28/2024 DAVID FEILER
CofO Issued 7/3/2024 DEROLD HAUFF
Permit Finaled 7/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/4/2022 STEVE MELGAR
Sewer availability Cleared 1/4/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 1/5/2022 STEVE MELGAR
Tenant Habitability Plan Cleared 1/18/2022 RICHARD BRINSON
CPC Cleared 5/5/2022 RICHARD REASER

Contact Information

Contractor Valencia Construction Company; Lic. No.: 1015167-B 12069 SMALLWOOD AVE      DOWNEY, CA 90242
Engineer Acciani,, Mark; Lic. No.: C83929 PO BOX 1390      RUNNING SPRINGS, CA 92382

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/7/2023 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/22/2023 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 10/23/2023 Approved STUART CHAPMAN
PLUMBING-Rough 10/23/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 11/6/2023 Partial Inspection CRAIG DAVIS
Insulation 11/6/2023 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 11/9/2023 Not Ready for Inspection CRAIG DAVIS
Underground Mechanical 11/9/2023 Partial Approval CRAIG DAVIS
Wood Frame 11/9/2023 Not Ready for Inspection CRAIG DAVIS
Wood Frame 11/21/2023 Partial Approval CRAIG DAVIS
Wood Frame 12/5/2023 Partial Inspection CRAIG DAVIS
Interior/Exterior Lathing 12/7/2023 Approved CRAIG DAVIS
Insulation 12/12/2023 Approved CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 12/18/2023 Approved CRAIG DAVIS
Drywall Nailing 1/4/2024 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 1/5/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/5/2024 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/8/2024 Partial Inspection MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 4/17/2024 SGSOV Not Ready CRAIG DAVIS
Final 5/6/2024 No Access for Inspection ANTHONY EGSON
Green Building Final 5/6/2024 No Access for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 5/6/2024 No Access for Inspection ANTHONY EGSON
ELECTRICAL-Final 5/9/2024 Corrections Issued CRAIG DAVIS
Final 5/9/2024 Corrections Issued CRAIG DAVIS
Green Building Final 5/9/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 5/9/2024 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 5/9/2024 Not Ready for Inspection CRAIG DAVIS
Final 5/14/2024 Not Ready for Inspection CRAIG DAVIS
Green Building Final 5/14/2024 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 5/14/2024 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 5/14/2024 Not Ready for Inspection CRAIG DAVIS
Final 6/20/2024 No Access for Inspection CRAIG DAVIS
Green Building Final 6/20/2024 No Access for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 6/20/2024 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 6/20/2024 No Access for Inspection CRAIG DAVIS
Final 6/25/2024 Corrections Issued CRAIG DAVIS
Green Building Final 6/25/2024 Approved CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 6/25/2024 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 6/25/2024 Approved CRAIG DAVIS
Final 6/27/2024 OK to Issue CofO DAVID FEILER
SGSOV-Seismic Gas S/O Valve 6/27/2024 SGSOV Approved DAVID FEILER
Service/Power Release 6/27/2024 Approved DAVID FEILER