22101 W ERWIN ST 1-62 91367
Certificate Information: 22101 W ERWIN ST 1-62 91367
- Application / Permit
- 21016-10000-32378
- Plan Check / Job No.
- B21LA18351
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT EXISITING STORAGE ROOM ON THE 1ST FLOOR TO ADU
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO Issued on 7/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2021 | APPLICANT |
| Corrections Issued | 10/18/2021 | RACHEL BEYENE |
| Assigned to Plan Check Engineer | 10/19/2021 | RACHEL BEYENE |
| Corrections Issued | 12/2/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 12/2/2021 | SHANGQIN XIE |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| Plan Check Approved | 1/5/2022 | DANIEL SANJUAN |
| Issued | 2/23/2022 | APPLICANT |
| CofO in Progress | 7/26/2022 | JEFFREY DURAN |
| CofO Issued | 7/26/2022 | JEFFREY DURAN |
| Permit Finaled | 7/26/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| ZI | Cleared | 11/10/2021 | LOUIS ORTEGA |
| Address approval | Cleared | 12/6/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/6/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/8/2021 | LEE GUILBEAUX |
Contact Information
| Architect | Dorman,, Christopher J; Lic. No.: C28300 | 229 FLAMINGO ROAD MILL VALLEY, CA 94941 |
| Contractor | Grundco; Lic. No.: 1016287-B | 24372 VANOWEN ST STE 205 WEST HILLS, CA 91307 |
| Engineer | Billante,, Ryan Dylan; Lic. No.: C58814 | 4377 SECOND ST PLEASANTON, CA 94566 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wall Anchors | 3/23/2022 | Approved | DANIEL VARNUM |
| Wood Frame | 3/23/2022 | Approved | DANIEL VARNUM |
| Insulation | 3/31/2022 | Approved | DANIEL VARNUM |
| Drywall Nailing | 4/5/2022 | Approved | DANIEL VARNUM |
| Final | 6/8/2022 | Partial Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/8/2022 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 6/8/2022 | Approved | DANIEL VARNUM |
| Final | 7/26/2022 | OK to Issue CofO | JEFFREY DURAN |