1257 W 23RD ST 90731
Certificate Information: 1257 W 23RD ST 90731
- Application / Permit
- 21016-10000-32037
- Plan Check / Job No.
- B21LA18159
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert part of detached garage into ADU.
- Permit Issued
- Issued on 1/18/2022
- Issuing Office
- Current Status
- CofO Issued on 5/18/2023
- Certificate of Occupancy
- 232016 - CofO Issued More Information
- 232016 - CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | JOE VO |
| Corrections Issued | 10/1/2021 | JOE VO |
| Plan Check Approved | 10/13/2021 | JOE VO |
| Issued | 1/18/2022 | APPLICANT |
| CofO in Progress | 5/16/2023 | JOHN KLARIN |
| Permit Finaled | 5/18/2023 | ANSON MAGLASANG |
| CofO Issued | 5/18/2023 | ANSON MAGLASANG |
| Permit Finaled | 5/18/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2021 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2021 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 10/12/2021 | JOSE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/17/2022 | No Access for Inspection | WILFRED LOMELI |
| Footing/Foundation/Slab | 3/18/2022 | Partial Approval | ROBERT STUCZYNSKI |
| Green Building Rough | 4/22/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 4/22/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Drywall Nailing | 5/16/2022 | Partial Approval | ANSON MAGLASANG |
| Interior/Exterior Lathing | 5/16/2022 | Approved | ANSON MAGLASANG |
| Final | 7/15/2022 | No Access for Inspection | ANSON MAGLASANG |
| Green Building Final | 7/15/2022 | No Access for Inspection | ANSON MAGLASANG |
| Green Building Rough | 7/15/2022 | No Access for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | No Access for Inspection | ANSON MAGLASANG |
| Smoke Detectors | 7/15/2022 | No Access for Inspection | ANSON MAGLASANG |
| Wood Frame | 7/15/2022 | No Access for Inspection | ANSON MAGLASANG |
| Final | 7/21/2022 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 7/21/2022 | Approved | ANSON MAGLASANG |
| Green Building Rough | 7/21/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV No Gas | ANSON MAGLASANG |
| Smoke Detectors | 7/21/2022 | Approved | ANSON MAGLASANG |
| Wood Frame | 7/21/2022 | Approved | ANSON MAGLASANG |
| Final | 8/12/2022 | Corrections Issued | ANSON MAGLASANG |
| Final | 9/13/2022 | Corrections Issued | ANSON MAGLASANG |
| Final | 10/4/2022 | No Access for Inspection | ANSON MAGLASANG |
| Final | 5/5/2023 | Off-Hour Fees Due | |
| Final | 5/15/2023 | OK to Issue CofO | JOHN KLARIN |