1212 S FLOWER ST 100 90015
Certificate Information: 1212 S FLOWER ST 100 90015
- Application / Permit
- 21016-10000-31986
- Plan Check / Job No.
- B21LA18146
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- EPLAN New Tenant Improvement to 11,182 sf of commercial space on ground floor space of existing 5 story office building
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Current Status
- Permit Finaled on 6/27/2023
Permit Application Status History
| Submitted | 9/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 10/16/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 10/25/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 1/8/2022 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 2/16/2022 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 3/9/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/21/2022 | ARSALAN SHABESTARI |
| Issued | 6/23/2022 | APPLICANT |
| Permit Finaled | 6/27/2023 | DARRYL ARNOLD |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 1/11/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 1/11/2022 | DAVID URITA |
| Green Code | Cleared | 1/31/2022 | ARSALAN SHABESTARI |
| DAS Clearance | Cleared | 2/10/2022 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Septon Development Group Inc; Lic. No.: 903427-B | 9545 E DOUBLETREE RANCH ROAD STE 150 SCOTTSDALE, AZ 85258 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/5/2022 | Approved | JAMES POWERS |
| Pre-Inspection | 10/26/2022 | Approved | KATY RAMIREZ |
| Light Gage Steel Frame | 11/21/2022 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 12/12/2022 | Approved | KATY RAMIREZ |
| T-Bar Ceiling | 1/5/2023 | Partial Approval | KATY RAMIREZ |
| T-Bar Ceiling | 2/3/2023 | Partial Approval | KATY RAMIREZ |
| Structural Steel Frame | 2/7/2023 | Partial Approval | KATY RAMIREZ |
| Special/Order Compliance | 2/15/2023 | Corrections Issued | KATY RAMIREZ |
| Pre-Inspection | 2/16/2023 | Partial Inspection | KATY RAMIREZ |
| Final | 3/6/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 3/9/2023 | Conditional Approval | ALFREDO LOPEZ |
| Green Building Final | 3/9/2023 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/9/2023 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 3/9/2023 | Approved | ALFREDO LOPEZ |
| Special/Order Compliance | 3/11/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 6/27/2023 | Permit Finaled | DARRYL ARNOLD |