8364 W 3RD ST 90048
Certificate Information: 8364 W 3RD ST 90048
- Application / Permit
- 21016-10000-31260
- Plan Check / Job No.
- B21LA18110
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Tatoo Studio
- Work Description
- CHANGE OF USE FROM RETAIL TO TATOO REMOVAL AND FADING FACILITY/OFFICE.TENANT IMPROVEMENT OF 1,138 S.F. BUSINESS. WORK TO INCLUDED NEW NON-STRUCTURAL PARTITIONS, CEILING, DOORS, FIXTURES, FINISHES.
- Permit Issued
- Issued on 3/8/2022
- Issuing Office
- Current Status
- CofO Issued on 5/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 10/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | MICHAEL LOPEZ |
| Corrections Issued | 10/21/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 10/28/2021 | KEN GILL |
| Plan Check Approved | 2/15/2022 | MICHAEL LOPEZ |
| Issued | 3/8/2022 | APPLICANT |
| Building Plans Picked Up | 3/15/2022 | APPLICANT |
| CofO in Progress | 5/24/2022 | KATY RAMIREZ |
| Permit Finaled | 5/27/2022 | ERNESTO CORRAL |
| CofO Issued | 5/27/2022 | ERNESTO CORRAL |
| Permit Finaled | 5/27/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| CPC | Cleared | 11/22/2021 | KENTON TRINH |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2021 | THAN WIN |
| DAS Clearance | Cleared | 1/6/2022 | SHINE LIN |
| Sewer availability | Cleared | 1/12/2022 | WALLIE JONG |
Contact Information
| Architect | Gallardo,, Conrado J; Lic. No.: C29223 | 10840 EBERLY COURT SAN DIEGO, CA 92126 |
| Contractor | Touchstone Contractors Inc; Lic. No.: 899558-B | 300 E BONITA AVENUE #4945 SAN DIMAS, CA 91773 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/18/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Footing/Foundation/Slab | 3/21/2022 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 3/30/2022 | Partial Inspection | KATY RAMIREZ |
| METHANE-Rough | 3/30/2022 | Approved | KATY RAMIREZ |
| Drywall Nailing | 4/7/2022 | Approved | KATY RAMIREZ |
| Insulation | 4/7/2022 | Approved | KATY RAMIREZ |
| Partition/T-Bar Ceiling | 4/25/2022 | Partial Inspection | KATY RAMIREZ |
| Final | 4/29/2022 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 4/29/2022 | Approved | KATY RAMIREZ |
| Wood Frame | 4/29/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 5/4/2022 | Partial Inspection | KATY RAMIREZ |
| Final | 5/24/2022 | OK to Issue CofO | KATY RAMIREZ |