2918 S FARMDALE AVE 90016
Certificate Information: 2918 S FARMDALE AVE 90016
- Application / Permit
- 21016-10000-31190
- Plan Check / Job No.
- B21LA18082
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF AN (E) 340 S.F. DETACHED GARAGE AND 188 S.F. ADDITION TO CREATE A 528 S.F. SINGLE STORY DETACHED ADU. NO EXTERIOR OR SITE WORK PROPOSED. UPGRADE ELECTRICAL SERVICE AND RELOCATE TO ADU.
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Current Status
- CofO Issued on 8/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2021 | TSE MING HUANG |
| Corrections Issued | 9/28/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 12/13/2021 | TSE MING HUANG |
| Plan Check Approved | 1/5/2022 | TSE MING HUANG |
| Issued | 1/24/2022 | APPLICANT |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| CofO in Progress | 7/15/2022 | STUART CHAPMAN |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
| CofO Issued | 8/13/2022 | DEROLD HAUFF |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2021 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2021 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 11/4/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 11/4/2021 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sveiven,, Shane; Lic. No.: C89133 | 1909 S ALMA STREET SAN PEDRO, CA 90731 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/8/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/17/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/7/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/7/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/7/2022 | Approved | STUART CHAPMAN |
| Sewer | 4/7/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 4/7/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/25/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 5/2/2022 | Corrections Issued | STUART CHAPMAN |
| Insulation | 5/6/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 5/11/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/23/2022 | No Access for Inspection | HORACE FULTZ |
| Interior/Exterior Lathing | 5/25/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Interior/Exterior Lathing | 5/31/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 5/31/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/16/2022 | Approved | STUART CHAPMAN |
| Final | 6/16/2022 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/16/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 6/16/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 6/29/2022 | Approved | STUART CHAPMAN |
| Final | 6/29/2022 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 6/29/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 6/29/2022 | Approved | STUART CHAPMAN |
| Final | 7/15/2022 | OK to Issue CofO | STUART CHAPMAN |
| Service/Power Release | 7/15/2022 | Approved | STUART CHAPMAN |