10750 W ESTHER AVE 90064

Certificate Information: 10750 W ESTHER AVE 90064

Application / Permit
21016-10000-31105
Plan Check / Job No.
B21LA18003
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REDESIGN AND RE-LAYOUT INTERIOR LAYOUT. ADD ONE BATHROOM IN EXISTING HOUSE. ALTER STRUCTURAL ELEMENTS OF SFD TO REMOVE LOAD BEARING WALLS.
Permit Issued
Issued on 11/23/2021
Issuing Office
Current Status
Permit Finaled on 5/3/2022

Permit Application Status History

Submitted 9/24/2021 APPLICANT
Assigned to Plan Check Engineer 9/28/2021 RICARDO RAMIREZ
Corrections Issued 9/28/2021 RICARDO RAMIREZ
Applicant returned to address corrections 10/20/2021 RICARDO RAMIREZ
Plan Check Approved 11/17/2021 RICARDO RAMIREZ
Issued 11/23/2021 APPLICANT
Building Plans Picked Up 11/24/2021 APPLICANT
Permit Finaled 5/3/2022 JOHNNY MIRANDA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/19/2021 MATTHEW JENKINS
Construction within easement Cleared 11/2/2021 TORI CHEN

Contact Information

Contractor Guan Edward Ze; Lic. No.: 863098-B 1500 BENITO AVENUE      ALHAMBRA, CA 91803
Engineer Xi,, Wang; Lic. No.: C85148 422 FALLINGSTAR      IRVINE, CA 92614

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/10/2021 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 12/15/2021 Approved EVAN COOPER
ELECTRICAL-Rough 1/18/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 1/18/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 2/1/2022 Corrections Issued OGANES TARAKHCHYAN
Shower Pan 2/2/2022 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 2/3/2022 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/4/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Approved JOHNNY MIRANDA
Insulation 2/4/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 2/4/2022 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 2/18/2022 Approved JOHNNY MIRANDA
Drywall Nailing 2/18/2022 Approved JOHNNY MIRANDA
Green Building Rough 2/18/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 2/18/2022 Approved JOHNNY MIRANDA
Final 5/3/2022 Permit Finaled JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/3/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 5/3/2022 Approved JOHNNY MIRANDA