2435 1/4-1/2 E SHOREDALE AVE 90031

Certificate Information: 2435 1/4-1/2 E SHOREDALE AVE 90031

Application / Permit
21016-10000-31064
Plan Check / Job No.
B21LA17968
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 1ST FLOOR GARAGE TO ACCESSORY DWELLING UNIT PER STATE LAW
Permit Issued
Issued on 1/5/2022
Issuing Office
Current Status
CofO Issued on 3/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2021 APPLICANT
Assigned to Plan Check Engineer 9/28/2021 LAWRENCE QUIRANTE
Corrections Issued 9/28/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 12/1/2021 GEORGE ALVAREZ
Plan Check Approved 12/22/2021 SAMUEL GONZALEZ
Issued 1/5/2022 APPLICANT
Building Plans Picked Up 1/10/2022 APPLICANT
CofO in Progress 2/14/2023 THOMAS LOGRASSO
CofO Issued 3/1/2023 DEROLD HAUFF
Permit Finaled 3/1/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/5/2021 THOMAS LANG
Sewer availability Cleared 10/5/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/6/2021 THOMAS LANG
Supp. Use District POD/CDO/TDO Cleared 11/16/2021 LOUIS ORTEGA
Tenant Habitability Plan Cleared 12/14/2021 RICARDO BOHORQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Alferez,, Vicente Narvaez; Lic. No.: C53875 460 E CARSON PLAZA DR STE 212      CARSON, CA 90746

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/9/2022 Approved THOMAS LOGRASSO
Wood Frame 6/9/2022 Corrections Issued THOMAS LOGRASSO
Insulation 6/17/2022 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 6/17/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Corrections Issued THOMAS LOGRASSO
Insulation 6/28/2022 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 7/1/2022 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Partial Approval THOMAS LOGRASSO
Green Building Final 9/23/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 9/23/2022 Approved THOMAS LOGRASSO
Pre-Inspection 9/23/2022 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Not Ready THOMAS LOGRASSO
Smoke Detectors 9/23/2022 Not Ready for Inspection THOMAS LOGRASSO
Wood Frame 9/23/2022 Approved THOMAS LOGRASSO
Final 11/15/2022 Corrections Issued THOMAS LOGRASSO
Green Building Final 11/15/2022 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 11/15/2022 Approved THOMAS LOGRASSO
Final 1/18/2023 Corrections Issued THOMAS LOGRASSO
Green Building Final 1/18/2023 Approved THOMAS LOGRASSO
Final 2/13/2023 OK to Issue CofO THOMAS LOGRASSO