633 W 5TH ST 54TH FLOOR 90731

Certificate Information: 633 W 5TH ST 54TH FLOOR 90731

Application / Permit
21016-10000-30928
Plan Check / Job No.
B21LA17832
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePLAN. INTERIOR TENANT IMPROVEMENT TO (E) HIGHRISE OFFICE AND COMMERCIAL KITCHEN. NEW WALLS, FINISHES, AND MILLWORK. STAIR REMOVAL AND INFILL.
Permit Issued
Issued on 2/11/2022
Issuing Office
Current Status
Issued on 2/11/2022

Permit Application Status History

Submitted 9/23/2021 APPLICANT
Assigned to Plan Check Engineer 9/27/2021 KEVIN MORALES
Corrections Issued 9/27/2021 KEVIN MORALES
Applicant returned to address corrections 11/22/2021 KEVIN MORALES
Plan Check Approved 1/18/2022 KEVIN MORALES
Issued 2/11/2022 APPLICANT

Permit Application Clearance Information

"D" conditions Cleared 10/15/2021 MAXFIELD VERMY
Miscellaneous Cleared 10/15/2021 MAXFIELD VERMY
ZA Case Cleared 10/15/2021 MAXFIELD VERMY
ZA Case Cleared 10/15/2021 MAXFIELD VERMY
ZA Case Cleared 10/15/2021 MAXFIELD VERMY
Food establishment approval Cleared 11/22/2021 LACDHS APPROVED
Fire Marshal Fire Life Safety Cleared 1/13/2022 DOMINIQUE MEDINA

Contact Information

Architect Algaze,, Nelson; Lic. No.: NA21090       ,
Contractor J R M Construction West Llc; Lic. No.: 1013928-B 959 SOUTH COAST DR #495      COSTA MESA, CA 92626
Engineer Eisenreich,, Stephan; Lic. No.: C77781 29163 VALLEY OAK PLACE      SANTA CLARITA, CA 91390

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 3/21/2022 Approved JOEY BUCHANAN
Light Gage Steel Frame 3/25/2022 Approved DARRYL ARNOLD
Structural Steel Frame 3/25/2022 Approved DARRYL ARNOLD
Deputy Wood Construction 3/31/2022 Conditional Approval TIMOTHY BUXTON
Light Gage Steel Frame 4/15/2022 Partial Approval TIMOTHY BUXTON
Drywall Nailing 4/26/2022 Approved TIMOTHY BUXTON
Insulation 4/26/2022 Approved TIMOTHY BUXTON
Light Gage Steel Frame 4/26/2022 Approved TIMOTHY BUXTON
Drywall Nailing 5/23/2022 Corrections Issued JONATHAN QUACH
Light Gage Steel Frame 6/13/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 6/14/2022 Partial Approval TIMOTHY BUXTON
Drywall Nailing 6/21/2022 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 6/21/2022 Approved TIMOTHY BUXTON
Structural Steel Frame 6/28/2022 Partial Approval TIMOTHY BUXTON
T-Bar Ceiling 8/17/2022 Approved TIMOTHY BUXTON
Final 9/9/2022 Not Ready for Inspection TIMOTHY BUXTON
Green Building Final 9/9/2022 Not Ready for Inspection TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 9/9/2022 SGSOV No Gas TIMOTHY BUXTON
Smoke Detectors 9/9/2022 Approved TIMOTHY BUXTON
Final 9/13/2022 Partial Inspection TIMOTHY BUXTON
Green Building Final 9/13/2022 Not Ready for Inspection TIMOTHY BUXTON
Green Building Rough 9/13/2022 Approved TIMOTHY BUXTON