3458 S CARMONA AVE 90016

Certificate Information: 3458 S CARMONA AVE 90016

Application / Permit
21016-10000-30900
Plan Check / Job No.
B21LA17820
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) 1 OF 2
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
Issued on 3/2/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/4/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 KEVIN MORALES
Corrections Issued 11/9/2021 KEVIN MORALES
Quality Review Completed 11/10/2021 EUGENE BARBEAU
Building Plans Picked Up 11/17/2021 APPLICANT
Applicant returned to address corrections 2/1/2022 KEVIN MORALES
Plan Check Approved 2/15/2022 KEVIN MORALES
Issued 3/2/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/3/2022 JEANIE LAM
Sewer availability Cleared 1/3/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/4/2022 JEANIE LAM

Contact Information

Contractor 1st Choice Design & Development; Lic. No.: 576474-B 2400 E KATELLA AVENUE #800      ANAHEIM, CA 92806
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/14/2022 Partial Approval JOSE AVILA
Footing/Foundation/Slab 9/16/2022 Approved JOSE AVILA
ELECTRICAL-Rough 5/4/2023 Approved STUART CHAPMAN
PLUMBING-Rough 5/4/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/7/2023 Corrections Issued JOSE AVILA
Special/Order Compliance 7/7/2023 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 8/15/2023 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 11/8/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 12/13/2023 Corrections Issued SCOTT FINNILA
HVAC-Rough 12/13/2023 Approved SCOTT FINNILA
BUILDING-Rough-Frame 12/22/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 12/22/2023 Approved JOAQUIN GREENOUGH
Insulation 2/20/2024 Approved STUART CHAPMAN
Drywall Nailing 3/1/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 3/1/2024 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 4/4/2024 Approved JOSH MEISTER
Service/Power Release 12/20/2024 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 10/20/2025 Corrections Issued WILLIAM SIERRA
Deputy Wood Construction 11/5/2025 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 11/10/2025 Corrections Issued WILLIAM SIERRA
Final 11/10/2025 Corrections Issued WILLIAM SIERRA
Green Building Final 11/10/2025 Corrections Issued WILLIAM SIERRA
HVAC-Final 11/10/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Final 11/10/2025 Corrections Issued WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Approved WILLIAM SIERRA
Smoke Detectors 11/10/2025 Approved WILLIAM SIERRA