1001 N SEWARD ST 90038

Certificate Information: 1001 N SEWARD ST 90038

Application / Permit
21016-10000-30821
Plan Check / Job No.
B21LA17758
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
INTERIOR T.I. OF FLOORS 3, 4, AND 5, NEW INTERIOR STAIR, NEW KITCHEN AND GREASE INTERCEPTOR, ROOFTOP EQUIPMENT INSTALLATION, STRUCTURAL UPGRADE WORK ON ALL FLOORS FROM LEVEL-1 TO LEVEL-5, WITH NO EXTERIOR WORK AND NO CHANGE TO FLOOR AREA. (DEFERRED SUBMITTALS: STORAGE RACKS & ROLLING STORAGE SYSTEM, WALK-IN REFRIGERATOR, KITCHEN)
Permit Issued
Issued on 4/12/2023
Issuing Office
Metro
Current Status
Permit Finaled on 2/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 YOUNG KIM
Corrections Issued 10/13/2021 YOUNG KIM
Quality Review Completed 10/21/2021 KEN GILL
Disabled Access Plans Picked Up 10/21/2021 APPLICANT
Building Plans Picked Up 10/22/2021 APPLICANT
Applicant returned to address corrections 11/19/2021 YOUNG KIM
Applicant returned to address corrections 11/30/2021 YOUNG KIM
Applicant returned to address corrections 12/7/2021 YOUNG KIM
Applicant returned to address corrections 1/19/2022 YOUNG KIM
Applicant returned to address corrections 7/15/2022 YOUNG KIM
Applicant returned to address corrections 8/30/2022 YOUNG KIM
Applicant returned to address corrections 12/6/2022 YOUNG KIM
Applicant returned to address corrections 1/19/2023 YOUNG KIM
Applicant returned to address corrections 2/6/2023 YOUNG KIM
Applicant returned to address corrections 2/8/2023 YOUNG KIM
Applicant returned to address corrections 2/21/2023 YOUNG KIM
Applicant returned to address corrections 2/24/2023 YOUNG KIM
Applicant returned to address corrections 3/16/2023 YOUNG KIM
Applicant returned to address corrections 3/24/2023 YOUNG KIM
Applicant returned to address corrections 3/30/2023 YOUNG KIM
Plan Check Approved 4/7/2023 YOUNG KIM
Issued 4/12/2023 APPLICANT
Permit Finaled 1/31/2024 MARTIN TAVITIAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/9/2021 KHOUNG LE
Green Code Cleared 12/10/2021 YOUNG KIM
Food Service Establishment Cleared 2/2/2022 KENNETH BROWNE
Sewer availability Cleared 3/29/2022 KHOUNG LE
DAS Clearance Cleared 11/3/2022 YOUNG KIM

Contact Information

Architect Brennan,, Ross A; Lic. No.: C27858 7008 SANTA MONICA BLVD      HOLLYWOOD, CA 90038
Contractor Clune Construction Company L P; Lic. No.: 732107-B 725 SOUTH FIGUEROA STREET   STE 300    LOS ANGELES, CA 90017
Engineer Mengelkoch,, Samuel Owen; Lic. No.: S5439 813 WILCOX AVE 203      LOS ANGELES, CA 90038

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 5/18/2023 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 5/23/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 6/26/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 6/27/2023 Partial Approval JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 6/27/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 7/5/2023 Partial Approval JEROME BLACKWOOD
T-Bar Ceiling 7/5/2023 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 7/20/2023 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 7/20/2023 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 8/10/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 8/21/2023 Approved RONALD JIMENEZ
T-Bar Ceiling 9/12/2023 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 9/14/2023 Partial Approval ALFREDO LOPEZ
Special/Order Compliance 9/29/2023 Not Ready for Inspection JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 10/4/2023 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 10/10/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 10/11/2023 Not Ready for Inspection JEROME BLACKWOOD
T-Bar Ceiling 11/3/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 11/6/2023 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 11/6/2023 Partial Approval RICARDO ROBLES
Drywall Nailing 11/7/2023 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 11/7/2023 Partial Approval RICARDO ROBLES
Special/Order Compliance 11/17/2023 Not Ready for Inspection MARTIN TAVITIAN
T-Bar Ceiling 11/17/2023 Not Ready for Inspection MARTIN TAVITIAN
Final 12/20/2023 Partial Approval RICARDO ROBLES
Green Building Final 12/20/2023 Approved RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Approved RICARDO ROBLES
Smoke Detectors 12/20/2023 Approved RICARDO ROBLES
Special/Order Compliance 12/20/2023 Partial Approval RICARDO ROBLES
Final 1/10/2024 Conditional Approval ALFREDO LOPEZ
T-Bar Ceiling 1/23/2024 Partial Approval ALFREDO LOPEZ
Final 1/31/2024 Permit Finaled MARTIN TAVITIAN