1001 N SEWARD ST 90038
Certificate Information: 1001 N SEWARD ST 90038
- Application / Permit
- 21016-10000-30821
- Plan Check / Job No.
- B21LA17758
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR T.I. OF FLOORS 3, 4, AND 5, NEW INTERIOR STAIR, NEW KITCHEN AND GREASE INTERCEPTOR, ROOFTOP EQUIPMENT INSTALLATION, STRUCTURAL UPGRADE WORK ON ALL FLOORS FROM LEVEL-1 TO LEVEL-5, WITH NO EXTERIOR WORK AND NO CHANGE TO FLOOR AREA. (DEFERRED SUBMITTALS: STORAGE RACKS & ROLLING STORAGE SYSTEM, WALK-IN REFRIGERATOR, KITCHEN)
- Permit Issued
- Issued on 4/12/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | YOUNG KIM |
| Corrections Issued | 10/13/2021 | YOUNG KIM |
| Quality Review Completed | 10/21/2021 | KEN GILL |
| Disabled Access Plans Picked Up | 10/21/2021 | APPLICANT |
| Building Plans Picked Up | 10/22/2021 | APPLICANT |
| Applicant returned to address corrections | 11/19/2021 | YOUNG KIM |
| Applicant returned to address corrections | 11/30/2021 | YOUNG KIM |
| Applicant returned to address corrections | 12/7/2021 | YOUNG KIM |
| Applicant returned to address corrections | 1/19/2022 | YOUNG KIM |
| Applicant returned to address corrections | 7/15/2022 | YOUNG KIM |
| Applicant returned to address corrections | 8/30/2022 | YOUNG KIM |
| Applicant returned to address corrections | 12/6/2022 | YOUNG KIM |
| Applicant returned to address corrections | 1/19/2023 | YOUNG KIM |
| Applicant returned to address corrections | 2/6/2023 | YOUNG KIM |
| Applicant returned to address corrections | 2/8/2023 | YOUNG KIM |
| Applicant returned to address corrections | 2/21/2023 | YOUNG KIM |
| Applicant returned to address corrections | 2/24/2023 | YOUNG KIM |
| Applicant returned to address corrections | 3/16/2023 | YOUNG KIM |
| Applicant returned to address corrections | 3/24/2023 | YOUNG KIM |
| Applicant returned to address corrections | 3/30/2023 | YOUNG KIM |
| Plan Check Approved | 4/7/2023 | YOUNG KIM |
| Issued | 4/12/2023 | APPLICANT |
| Permit Finaled | 1/31/2024 | MARTIN TAVITIAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2021 | KHOUNG LE |
| Green Code | Cleared | 12/10/2021 | YOUNG KIM |
| Food Service Establishment | Cleared | 2/2/2022 | KENNETH BROWNE |
| Sewer availability | Cleared | 3/29/2022 | KHOUNG LE |
| DAS Clearance | Cleared | 11/3/2022 | YOUNG KIM |
Contact Information
| Architect | Brennan,, Ross A; Lic. No.: C27858 | 7008 SANTA MONICA BLVD HOLLYWOOD, CA 90038 |
| Contractor | Clune Construction Company L P; Lic. No.: 732107-B | 725 SOUTH FIGUEROA STREET STE 300 LOS ANGELES, CA 90017 |
| Engineer | Mengelkoch,, Samuel Owen; Lic. No.: S5439 | 813 WILCOX AVE 203 LOS ANGELES, CA 90038 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 4/26/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Light Gage Steel Frame | 5/18/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 5/23/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 6/26/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 6/27/2023 | Partial Approval | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 6/27/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 7/5/2023 | Partial Approval | JEROME BLACKWOOD |
| T-Bar Ceiling | 7/5/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 7/20/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 7/20/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 8/10/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 8/21/2023 | Approved | RONALD JIMENEZ |
| T-Bar Ceiling | 9/12/2023 | Partial Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 9/14/2023 | Partial Approval | ALFREDO LOPEZ |
| Special/Order Compliance | 9/29/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 10/4/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 10/10/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/11/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| T-Bar Ceiling | 11/3/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 11/6/2023 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 11/6/2023 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 11/7/2023 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 11/7/2023 | Partial Approval | RICARDO ROBLES |
| Special/Order Compliance | 11/17/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| T-Bar Ceiling | 11/17/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 12/20/2023 | Partial Approval | RICARDO ROBLES |
| Green Building Final | 12/20/2023 | Approved | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 12/20/2023 | Approved | RICARDO ROBLES |
| Special/Order Compliance | 12/20/2023 | Partial Approval | RICARDO ROBLES |
| Final | 1/10/2024 | Conditional Approval | ALFREDO LOPEZ |
| T-Bar Ceiling | 1/23/2024 | Partial Approval | ALFREDO LOPEZ |
| Final | 1/31/2024 | Permit Finaled | MARTIN TAVITIAN |