2242 1/2 S BURNSIDE AVE 90016
Certificate Information: 2242 1/2 S BURNSIDE AVE 90016
- Application / Permit
- 21016-10000-30799
- Plan Check / Job No.
- B21LA17736
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) RECREATION ROOM/STORAGE BLDG. INTO A.D.U. (380 SF) PER STATE LAW.
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/25/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/17/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 1/10/2022 | ADAM HEGAZI |
| Applicant returned to address corrections | 4/4/2022 | LUKE GONZALES |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Plan Check Approved | 7/21/2022 | ZAW HAN |
| Issued | 8/2/2022 | APPLICANT |
| CofO in Progress | 3/1/2023 | JOSE AVILA |
| Permit Finaled | 3/6/2023 | DEROLD HAUFF |
| CofO Issued | 3/6/2023 | DEROLD HAUFF |
| Permit Finaled | 3/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/1/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 11/1/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2021 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 2/24/2022 | RICHARD BRINSON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/29/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 9/2/2022 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 10/18/2022 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 10/18/2022 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 10/24/2022 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 11/3/2022 | Approved | JOSE AVILA |
| Sewer | 11/3/2022 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 11/14/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 11/14/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Approved | JOSE AVILA |
| Green Building Rough | 11/14/2022 | Corrections Issued | JOSE AVILA |
| MERV13>=Rough | 11/14/2022 | Conditional Approval | JOSE AVILA |
| PLUMBING-Rough | 11/14/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 11/21/2022 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 11/21/2022 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 11/21/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 11/23/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/23/2022 | Approved | STUART CHAPMAN |
| Insulation | 12/1/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/1/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 12/9/2022 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/20/2023 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Final | 1/20/2023 | Corrections Issued | JOSE AVILA |
| Final | 1/20/2023 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 1/20/2023 | Approved | JOSE AVILA |
| HVAC-Final | 1/20/2023 | Corrections Issued | JOSE AVILA |
| MERV13>=Final | 1/20/2023 | Approved | JOSE AVILA |
| MERV13>=Rough | 1/20/2023 | Approved | JOSE AVILA |
| PLUMBING-Final | 1/20/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 2/1/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/1/2023 | Approved | JOSE AVILA |
| Green Building Final | 2/1/2023 | Approved | JOSE AVILA |
| HVAC-Final | 2/1/2023 | Approved | JOSE AVILA |
| PLUMBING-Final | 2/1/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 2/1/2023 | Approved | JOSE AVILA |
| Final | 3/1/2023 | OK to Issue CofO | JOSE AVILA |